Title: Approve and authorize Agreement No. 8675 with Caltrans for the relinquishment of State Right of Way (ROW) necessary for the Construction of the Napa County Soscol Ferry Road/Devlin Road Roundabout Project. (No Fiscal Impact)
Sponsors: Board of Supervisors
Attachments: 1. Agreement
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TO: Board of Supervisors
FROM: Steve Lederer, Director of Public Works
REPORT BY: Juan Arias, Deputy Director of Public Works
SUBJECT: Soscol Ferry Road/Devlin Road Roundabout Project - Caltrans Relinquishment Agreement

RECOMMENDATION
title
Approve and authorize Agreement No. 8675 with Caltrans for the relinquishment of State Right of Way (ROW) necessary for the Construction of the Napa County Soscol Ferry Road/Devlin Road Roundabout Project. (No Fiscal Impact)
body
BACKGROUND
The proposed Devlin Roundabout project is located at the intersection of Devlin Road and Soscol Ferry Road in Napa County. This project is adjacent to Highway 29 which is State ROW. Construction of the roundabout requires minor changes to Soscol Ferry Road and the new Soscol Junction roundabout. As a result, a portion of the State ROW will be impacted and require modifications of the current access control. Caltrans has determined that the appropriate process to modify the access control, which will transfer a portion of State ROW to Napa County, is a Relinquishment Agreement. Therefore, Caltrans and Napa County need to approve the Relinquishment Agreement in order to move forward with the project. The project is scheduled to start construction this Fall contingent upon finalization of the relinquishment process with Caltrans.

Requested action:
Approve and authorize Agreement No. 8675 for the relinquishment of State Right of Way necessary for the Construction of the Napa County Soscol Ferry Road/Devlin Road Roundabout Project.

FISCAL & STRATEGIC PLAN IMPACT
Is there a Fiscal Impact?
No
Is it Mandatory or Discretionary?
Discretionary

ENVIRONMENTAL IMPACT
ENVIRONMENTAL DETERMINATION: A Mitigated Negative Declaration and Mitigation Monitoring and Reporting Program were adopted by the Board of Supervisors on August 17, 2021, for the Soscol Ferry Road - Devlin Road Intersection Roundabout Project (SCH #2021070257) pursuant to Resolution No. 2021-92. There have been no substantial chan...