File #: 23-0986    Version: 1
Type: Report Status: Agenda Ready
File created: 5/26/2023 In control: Board of Supervisors
On agenda: 6/6/2023 Final action:
Title: Director of Public Works requests the following actions regarding the 2023 Berryessa Improvements Project, specifically for RDS 23-05 Spanish Flat Loop Road Resurfacing (4/5 vote required): 1. Approval of and authorization for the Director of Public Works to sign contract change orders to the contract with Goodfellow Bros. for a maximum not to exceed amount of $254,857 to respond to unexpected circumstances during construction at the Project; 2. Board adoption of the findings expanded upon in this Board item; namely that changed conditions exist and public bidding would not produce an advantage and would be inappropriate, impractical, and not in the County's best interest due to the circumstances discussed in this Board item; 3. Increase appropriations by $254,856 in Accumulated Capital Outlay Fund (ACO) (Fund 3000, Org 3000000, Object 56100) offset using available fund balance to fund the Spanish Flat Loop Road Project (Fund 2040, Org 2040500, Project 23040, Object 4820...
Sponsors: Board of Supervisors
Attachments: 1. Updated Budget
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TO: Board of Supervisors
FROM: Steven Lederer - Director of Public Works
REPORT BY: Sydney Diede - Assistant Engineer
SUBJECT: Approve Contract Change Orders and Budget Transfer for the Spanish Flat Loop Road Resurfacing Project, RDS 23-05


RECOMMENDATION
title
Director of Public Works requests the following actions regarding the 2023 Berryessa Improvements Project, specifically for RDS 23-05 Spanish Flat Loop Road Resurfacing (4/5 vote required):
1. Approval of and authorization for the Director of Public Works to sign contract change orders to the contract with Goodfellow Bros. for a maximum not to exceed amount of $254,857 to respond to unexpected circumstances during construction at the Project;
2. Board adoption of the findings expanded upon in this Board item; namely that changed conditions exist and public bidding would not produce an advantage and would be inappropriate, impractical, and not in the County's best interest due to the circumstances discussed in this Board item;
3. Increase appropriations by $254,856 in Accumulated Capital Outlay Fund (ACO) (Fund 3000, Org 3000000, Object 56100) offset using available fund balance to fund the Spanish Flat Loop Road Project (Fund 2040, Org 2040500, Project 23040, Object 48200); and
4. Increase appropriations by $254,856 in Project 23040 (Fund 2040, Org 2040500, Project 23040, Object 52360) offset by a transfer-in revenue from ACO.
body

EXECUTIVE SUMMARY
The 2023 Berryessa Improvements Project is comprised of five (5) different projects in close proximity to each other, which includes: Berryessa Knoxville Road (RDS 22-05), Berryessa Highlands (RDS 22-13), Berryessa Pines (RDS 23-05), Spanish Flat Loop Road (RDS 23-05), and Steele Canyon Road (RDS 23-16). On April 18, 2023, the Board of Supervisors awarded a $5,117,222 contract to Goodfellow Bros.

During construction of the project, it was determined that the bid quantities for Hot Mix Asphalt and Monument Lid Installation would need to ...

Click here for full text