Title: Director of Public Works requests adoption of a Resolution amending the County's Policy Manual Part III, Fees, Part 30 Airport, effective July 1, 2023, increasing hangar and storage room fees by 7.6% and amending hangar descriptions.
Sponsors: Board of Supervisors
Attachments: 1. Resolution, 2. Exhibit A Airport Fees 2023 (Tracked), 3. Exhibit B Airport Fees 2023 (Clean)
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TO: Board of Supervisors
FROM: Steven Lederer, Director of Public Works
REPORT BY: Mark Witsoe, Airport Manager
SUBJECT: Adoption of a Resolution Amending Fees and Amending Hangar Descriptions at the Napa County Airport


RECOMMENDATION
title
Director of Public Works requests adoption of a Resolution amending the County's Policy Manual Part III, Fees, Part 30 Airport, effective July 1, 2023, increasing hangar and storage room fees by 7.6% and amending hangar descriptions.
body

EXECUTIVE SUMMARY
Adoption of the resolution will amend Part III, Fees, Part 30 Airport, within the County's Policy Manual by modifying those fees as shown by strike-out in Exhibit "A" of the resolution. The proposed increase to the hangar and storage room rates is tied to the June 2021 to June 2022 Annual Consumer Price Index (CPI) for Urban Wage Earners and Clerical workers for San Francisco-Oakland-Hayward. The proposed adjustment will increase Airport revenues in Fiscal Year 2023-24 by approximately $15,743.

FISCAL & STRATEGIC PLAN IMPACT
Is there a Fiscal Impact?
Yes
Is it currently budgeted?
No
Where is it budgeted?
The modified rates have been incorporated into the recommended budget for the Airport Enterprise Fund for Fiscal Year 2023-24.
Is it Mandatory or Discretionary?
Discretionary
Discretionary Justification:
The fee amendment will increase rents and fees by CPI and will result in additional annual revenue of approximately $15,743 during fiscal year 2023-24. As utility maintenance costs continue to rise for hangars, doors, and gates, additional revenue is needed in order to continue with preventative maintenance activities.
Is the general fund affected?
No
Future fiscal impact:
Amending fees will assist the Airport in collecting an additional $15,743 per year until such time as the fees are amended again. The proposed fees have been incorporated into the recommended budget for Fiscal Year 2023-24.
Consequences if not approved:
If not approved, the Napa County Airport woul...