File #: 24-313    Version: 1
Type: Agreement Status: Agenda Ready
File created: 2/14/2024 In control: Board of Supervisors
On agenda: 2/27/2024 Final action:
Title: Approve and authorize Agreement No. 240283B with Bureau Veritas for a contract maximum of $895,774 for construction management services and Amendment No. 3 to Agreement No. 170727B with Biggs Cardosa Associates, Inc., for a contract maximum of $275,212 for design services to support the construction of the Chiles Pope Valley Road Bridge. (Fiscal Impact: $1,170,986; Roads Fund; Budgeted; Discretionary) [4/5 vote required]
Sponsors: Board of Supervisors
Attachments: 1. Project Budget, 2. Agreement - Bureau Veritas, 3. Agreement - Biggs Cardosa Associates, Inc.
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TO: Board of Supervisors
FROM: Steven Lederer - Director of Public Works
REPORT BY: James Reese, P.E. - Associate Engineer
SUBJECT: Award of Professional Services Agreement No. 240283B to Bureau Veritas, and Amendment No. 3 to Professional Services Agreement No. 170727B to Biggs Cardosa Associates, Inc. for the Chiles-Pope Valley Road Bridge Replacement Project, RDS 15-23

RECOMMENDATION
title
Approve and authorize Agreement No. 240283B with Bureau Veritas for a contract maximum of $895,774 for construction management services and Amendment No. 3 to Agreement No. 170727B with Biggs Cardosa Associates, Inc., for a contract maximum of $275,212 for design services to support the construction of the Chiles Pope Valley Road Bridge. (Fiscal Impact: $1,170,986; Roads Fund; Budgeted; Discretionary)
[4/5 vote required]
body
BACKGROUND
The Chiles Pope Valley Bridge Replacement Project, RDS 15-23 is scheduled to begin construction in late March or early April, and construction management services are required. Bureau Veritas was selected as the most qualified candidate by a two-step RFQ/RFP process to provide these services which includes onsite construction, inspection, and contract management. Biological inspections, labor compliance, coordinating between the contractor, permit agencies, engineers and County are part of their scope of work.
Biggs Cardosa Associates, Inc. designed the project, prepared the bid documents and is needed for engineering construction services. It is an industry practice for the design consultant to answer contractor requests for information, approve material submittals, and provide engineering services during construction. The scope and fee for this was not included in the original agreement because, at that time, the exact design solution is not known.
The Napa County Public Works Department is responsible for maintaining 78 bridges that are included in the National Bridge Inventory. The County built the Chiles Pope Valley Road Bridge in...