Title: Approve plans and specifications for the "Taxiway K and Runway 19R Run-up Apron Reconstruction Project," PW 24-04, and authorize staff to advertise sealed bids and open bids at a time, date, and location to be published by the Director of Public Works pursuant to Section 20150.8 of the Public Contract Code. (No Fiscal Impact; Discretionary)
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TO: Board of Supervisors
FROM: Steven Lederer, Director of Public Works
REPORT BY: Katherine Bales, Assistant Airport Manager
SUBJECT: Taxiway K and Runway19R Run-up Apron Reconstruction Project - Approval of Plans and Specifications and Authorization to Advertise

RECOMMENDATION
title
Approve plans and specifications for the "Taxiway K and Runway 19R Run-up Apron Reconstruction Project," PW 24-04, and authorize staff to advertise sealed bids and open bids at a time, date, and location to be published by the Director of Public Works pursuant to Section 20150.8 of the Public Contract Code. (No Fiscal Impact; Discretionary)
body
BACKGROUND
In order to provide for the continuous safety of aircraft operations at the Napa County Airport, Airport management worked closely with the Federal Aviation Administration (FAA) to identify several runway and taxiway maintenance tasks that are necessary over the next five to ten years and are Airport Improvement Program (AIP) eligible. The next programmed project in this effort involves the reconstruction of failing pavement on Taxiway K as well as expansion of an aircraft run-up area that has been deemed by the FAA to be undersized for the classification of aircraft using the airport.

Taxiway K pavement has not been rehabilitated since it was originally constructed in 1986, is one of the most used taxiways in our system, and has been given a pavement classification of "very poor," with a Pavement Condition Index (PCI) of 28. The Taxiway K connector to Runway 19R was rehabilitated as a part of the Runway Rehabilitation project in 2019. Construction of Taxiway K is programmed by the FAA for a grant in Federal Fiscal Year 2024 (Napa County FY 24-25). To prepare for construction, the Airport funded the National Environmental Policy Act (NEPA) Categorical Exemption and California Environmental Quality Act (CEQA) reviews as well as project design. These costs will be included in the final grant application for reimbursement, in a...