FROM: Richard Thomasser - District Manager
REPORT BY: Andrew Butler - District Engineer
SUBJECT: Napa River/Napa Creek Flood Protection Project (Flood Project) Update


RECOMMENDATION
title
District staff to present an update on the Flood Project.
body

EXECUTIVE SUMMARY
The District Manager and District Engineer will present a status update on the Flood Project regarding the progress towards a process to construct the Floodwalls North of the Bypass Project (Floodwalls Project) in cooperation with the United States Army Corps of Engineers (USACE); the progress on the early design efforts for the Floodwalls Project; the recent public meetings soliciting feedback and input on the design of this project and the future construction activities, and the progress on the Real Estate Acquisition Plan.

FISCAL IMPACT
Is there a Fiscal Impact?
No

ENVIRONMENTAL IMPACT
ENVIRONMENTAL DETERMINATION: The proposed action is not a project as defined by 14 California Code of Regulations 15378 (State CEQA Guidelines) and therefore CEQA is not applicable.

BACKGROUND AND DISCUSSION
District staff have been working to advance certain aspects of the Flood Project in anticipation of preparing for construction of the next phase - the Floodwalls Project, which will provide flood protection north of the downtown dry bypass channel. Currently the District is working with the office of the Assistant Secretary of the Army on a strategy to meet the federal requirements to move forward with the project. This process is expected to take place over the next few months. After this, the District is expected to continue work on the design of the Floodwalls Project through 2023. To this end, staff have selected HDR, Inc. to assist in the design. HDR has a great deal of experience with the Flood Project. The Board of Directors approved HDR's design contract at the December 7, 2021 Board Meeting.

Real Estate Acquisition - the District, as the local sponsor for the Fl...