Napa County Logo
File #: 22-1378    Version: 1
Type: Report Status: Agenda Ready
File created: 7/5/2022 In control: Board of Supervisors
On agenda: 7/12/2022 Final action:
Title: Director of Public Works requests approval of the following budget transfers for five 2023 Roadway Seals Projects (4/5 vote required): 1. Increase appropriations by $75,000 in Measure T Non-Operating Special Revenue Fund (Fund 2440, Org 1220053) (M-T SRF) offset by use of its available fund balance as soon as the next quarterly disbursement becomes available (end of July, 2022) for $75,000: a. Increase appropriations by $15,000 in American Canyon Road Repair Project (Fund 2040, Org 2040500, Project 22026) offset by transfer from M-T SRF; b. Creation of a new project for Berryessa Knoxville Road FLAP 1 Seal (Fund 2040, Org 2040500, Project 22027) and increase appropriations by $15,000 offset by transfer from M-T SRF; c. Creation of a new project for Redwood Road Seal (Fund 2040, Org 2040500, Project 23007) and increase appropriations by $15,000 offset by transfer from M-T SRF; d. Creation of a new project for Old Howell Mountain Road Seal (Fund 2040, Org 2040500, Project 23008) and incr...
Attachments: 1. Five Seals-Budget-2022
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TO: Board of Supervisors
FROM: Steven Lederer, Director of Public Works
REPORT BY: Sydney Diede, Assistant Engineer
SUBJECT: Budget Transfer for Preliminary Design of Five (5) Roadway Seals Project: American Canyon Road (RDS 22-04), Berryessa Knoxville Road FLAP 1 (RDS 22-05), Redwood Road (RDS 23-02), Old Howell Mountain Road (RDS 23-03), and Wooden Valley Road (RDS 23-04).


RECOMMENDATION
title
Director of Public Works requests approval of the following budget transfers for five 2023 Roadway Seals Projects (4/5 vote required):
1. Increase appropriations by $75,000 in Measure T Non-Operating Special Revenue Fund (Fund 2440, Org 1220053) (M-T SRF) offset by use of its available fund balance as soon as the next quarterly disbursement becomes available (end of July, 2022) for $75,000:
a. Increase appropriations by $15,000 in American Canyon Road Repair Project (Fund 2040, Org 2040500, Project 22026) offset by transfer from M-T SRF;
b. Creation of a new project for Berryessa Knoxville Road FLAP 1 Seal (Fund 2040, Org 2040500, Project 22027) and increase appropriations by $15,000 offset by transfer from M-T SRF;
c. Creation of a new project for Redwood Road Seal (Fund 2040, Org 2040500, Project 23007) and increase appropriations by $15,000 offset by transfer from M-T SRF;
d. Creation of a new project for Old Howell Mountain Road Seal (Fund 2040, Org 2040500, Project 23008) and increase appropriations by $15,000 offset by transfer from M-T SRF; and
e. Creation of a new project for Wooden Valley Road Seal (Fund 2040, Org 2040500, Project 23009) and increase appropriations by $15,000 offset by transfer from M-T SRF.
body

EXECUTIVE SUMMARY
The Five (5) Roadway Seals Project will occur at the following road locations (the exact locations and project limits will be determined during the design):
1. American Canyon Road (City Line to Highway 80)
2. Berryessa Knoxville Road (Spanish Flat to Putah Creek)
3. Old Howell Mountain Road (St. Helena city line to approximately C...

Click here for full text