Title: Director of Public Works requests approval of and authorization for the Chair to sign Amendment No. 6 to Agreement 130004B with ESA PWA (ESA), increasing the maximum compensation by $244,300 for a new maximum of $4,896,535 for the purpose of providing additional hydraulic analysis required to prepare a Letter of Map Revision (LOMR) application for the Napa River Oakville to Oak Knoll (OVOK) Restoration Project.
Attachments: 1. Agreement
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TO: Board of Supervisors
FROM: Steven Lederer - Director of Public Works
REPORT BY: Michael Gordon - Watershed and Flood Control Resources Specialist
SUBJECT: Amendment No. 6 to Napa County Agreement No. 130004B with ESA PWA - Napa River Oakville to Oak Knoll Restoration Project Hydraulic Analysis


RECOMMENDATION
title
Director of Public Works requests approval of and authorization for the Chair to sign Amendment No. 6 to Agreement 130004B with ESA PWA (ESA), increasing the maximum compensation by $244,300 for a new maximum of $4,896,535 for the purpose of providing additional hydraulic analysis required to prepare a Letter of Map Revision (LOMR) application for the Napa River Oakville to Oak Knoll (OVOK) Restoration Project.
body

EXECUTIVE SUMMARY
Channel restoration projects have been constructed on the Napa River in the Rutherford and OVOK reaches. In the Rutherford reach, ESA began to develop a LOMR based on the 2008 Conditional Letter of Map Revision (CLOMR) and as-built survey data for the constructed project. In the OVOK reach, ESA submitted certified individual No-Rise studies for the restoration sites in each of the construction groups (A-D). ESA proposes to combine these reaches into a single LOMR extending from Zinfandel Lane to Oak Knoll Avenue which will be submitted to the County floodplain manager and the Federal Emergency Management Agency (FEMA).

FISCAL & STRATEGIC PLAN IMPACT
Is there a Fiscal Impact?
Yes
Is it currently budgeted?
Yes
Where is it budgeted?
Fund: 1000 Organization: 1220500 Project: 07002
Is it Mandatory or Discretionary?
Discretionary
Discretionary Justification:
Amendment 6 is needed to complete the hydraulic analysis that will support the LOMR for the entire OVOK project.
Is the general fund affected?
No
Future fiscal impact:
No
Consequences if not approved:
The analysis will not be able to be completed with the current balance of contract funds.
County Strategic Plan pillar addressed:
Vibrant and Sustainable Environment
...