Title: Director of Public Works requests approval of and authorization for the Chair to sign Amendment No. 1 to Agreement No. 220084B with Global Stabilization, LLC., increasing the amount by $41,976 to a new maximum of $324,876 and amending the scope of work to include application of EBS RA topical application (a "Fog Seal") on various completed paving projects.
Sponsors: Board of Supervisors
Attachments: 1. Agreement
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TO: Board of Supervisors
FROM: Steven Lederer - Director of Public Works, Roads Department
REPORT BY: Michael Parker - Supervising Staff Services Analyst
SUBJECT: Amendment No. 1 to Agreement No. 220084B with Global Stabilization, LLC


RECOMMENDATION
title
Director of Public Works requests approval of and authorization for the Chair to sign Amendment No. 1 to Agreement No. 220084B with Global Stabilization, LLC., increasing the amount by $41,976 to a new maximum of $324,876 and amending the scope of work to include application of EBS RA topical application (a "Fog Seal") on various completed paving projects.
body

EXECUTIVE SUMMARY
Today's requested action is for approval of Amendment No. 1 to Agreement No. 220084B with Global Stabilization, LLC. The County, in conjunction with Global Stabilization, has recently completed paving on Olive Hill Lane, Mt. George Ave., West Zinfandel Lane, and Finnell Road. Based on recommendations from our Geotechnical engineer, staff has determined the addition of a fog seal over the new pavement will add several year's life to the pavement. This amendment will increase the contract maximum to allow for Global Stabilization staff to apply 353,860 square feet of EBS RA topical application to these projects.

FISCAL & STRATEGIC PLAN IMPACT
Is there a Fiscal Impact?
Yes
Is it currently budgeted?
Yes
Where is it budgeted?
Costs will be incurred in Roads Operations sub-division 2040000 but will be reimbursed from the PG&E Settlement Funds for Roads. This cost is within the approved project budget.
Is it Mandatory or Discretionary?
Discretionary
Discretionary Justification:
The application of a topical solution to ambient temperature asphalt is needed for a currently scheduled Road's project.
Is the general fund affected?
No
Future fiscal impact:
There is no planned future fiscal impact.
Consequences if not approved:
If this item is not approved, these roads will not benefit from the addition of a fog seal.