File #: 21-118    Version: 1
Type: Report Status: Agenda Ready
File created: 4/14/2021 In control: Board of Supervisors
On agenda: 5/4/2021 Final action:
Title: Director of Public Works requests: 1. Creation of a new Capital Improvement Project (CIP) within the Public Works Capital Improvement Program budget (Fund 2040, Sub-Division 2040500) for East Central Paving Project, RDS21-25 (Program 21067); and 2. Approval of Budget Transfer No. DPW054 for the following (4/5 vote required): a. Increase appropriation by $5,250,000 in the Accumulated Capital Outlay Fund (Fund 3000, Sub-Division 300000) offset by the revenue from the General Fund Non-Departmental budget to fund the preliminary evaluation, design and engineering, and construction of the project; and b. Increase appropriations by $5,250,000 in East Central Paving Project (Fund 2040, Sub-Division 2040500, program 21067) budget with offsetting revenue from the transfer from the Accumulated Capital Outlay Fund.
Sponsors: Board of Supervisors
Attachments: 1. East Central Paving_Agenda Item Budget Sheet.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.



TO: Board of Supervisors
FROM: Steven Lederer - Director of Public Works
REPORT BY: Liang Chin Su, Junior Engineer - 7072598376
SUBJECT: Creation of a new Capital Improvement Project (CIP) East Central Paving Project, RDS 21-25 and Budget Transfer


RECOMMENDATION
title
Director of Public Works requests:
1. Creation of a new Capital Improvement Project (CIP) within the Public Works Capital Improvement Program budget (Fund 2040, Sub-Division 2040500) for East Central Paving Project, RDS21-25 (Program 21067); and
2. Approval of Budget Transfer No. DPW054 for the following (4/5 vote required):
a. Increase appropriation by $5,250,000 in the Accumulated Capital Outlay Fund (Fund 3000, Sub-Division 300000) offset by the revenue from the General Fund Non-Departmental budget to fund the preliminary evaluation, design and engineering, and construction of the project; and
b. Increase appropriations by $5,250,000 in East Central Paving Project (Fund 2040, Sub-Division 2040500, program 21067) budget with offsetting revenue from the transfer from the Accumulated Capital Outlay Fund.

end

EXECUTIVE SUMMARY
The County has received funds from Pacific Gas and Electric (PG&E) as a settlement for damages caused by the 2017 North Bay fires. The Board has designated $16 million of this funding towards road repairs. This agenda item authorizes $5,250,000 in funding for a project to conduct repairs on the following damaged roads:
* Atlas Peak Road (SR 121 to Westgate)
* Hillcrest Drive (All)
* Westgate Drive (All)
* Soda Canyon Road (Silverado Trail to Loma Vista)
* Second Avenue (All)
* Vichy Avenue (All).

FISCAL & STRATEGIC PLAN IMPACT

Is there a Fiscal Impact? Yes
Is it currently budgeted? No
Where is it budgeted? Revenue Source: PG&E Settlement Funds in the General Fund Non-Departmental Budget. $5.25 million request is being moved from the Non-Departmental Budget to the Accumulated Capital Outlay Fund, then it will be moved to the Roads CIP project budget.
...