Skip to main content
Napa County Logo
File #: 25-1296    Version: 1
Type: HC Monthly Reports Status: Agenda Ready
File created: 7/8/2025 In control: Housing Commission
On agenda: 7/23/2025 Final action:
Title: Monthly report on capital improvement projects (CIP).
Attachments: 1. Capital Improvement Projects
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

 

TO:                     Napa County Housing Commission

FROM:                     Jennifer Palmer, Executive Director of Housing Authority

REPORT BY:                     Alex Carrasco, Project Manager

SUBJECT:                                          Monthly report on capital improvement projects (CIPs)

 

RECOMMENDATION

title

Monthly report on capital improvement projects (CIP).

body

EXECUTIVE SUMMARY

Each month, staff report on capital improvement projects for each of the three farmworker centers. Over the course of the prior three months, staff have also reported on critical repairs and essential equipment. During this time, the list of “High” priority items has increased substantially while funding resources remain limited. Last month, an ad hoc committee was formed to assist staff in developing new guidelines for the priority items.

PROCEDURAL REQUIREMENTS
1. Staff Report.
2. Public Comment.
3. Discussion.

 

ENVIRONMENTAL IMPACT

ENVIRONMENTAL DETERMINATION: The proposed action is not a project as defined by 14 California Code of Regulations 15378 (State CEQA Guidelines) and therefore CEQA is not applicable.

 

BACKGROUND AND DISCUSSION

In December 2023, Housing Authority staff presented the Housing Commissioners with the list of capital improvements needs identified by County and CHDC staff.  This list included summary of project scope and budgets based on informal solicitation of project estimates by related service providers.  The list was sorted by health and safety impact needs and projects were ranked “High, “Medium”, and “Low” priority.  Additionally, available funding sources - including donor-advised funds from the Farmworker Committee - were noted for each potential project.  Housing Commissioners discussed the scope of needs and available funds and recommended staff proceed with securing estimates and submitting budget adjustments to proceed immediately with all items identified as “High” priority items.