TO: Board of Supervisors
FROM: Steven Lederer, Director of Public Works
REPORT BY: Steven Lederer, Director of Public Works
SUBJECT: Project Creation, Budget Amendment, and authorization to pay invoice for the "2025 Oakville Grade RR Crossing Repair, RDS 25-101"
RECOMMENDATION
title
Approve and authorize the creation of Project 25032 for the "2025 Oakville Grade Railroad Crossing Repair", RDS 25-101"; approve a Budget Amendment; and authorize the payment of an invoice for work completed. (Fiscal Impact: $47,209 Expense; SB-1 Non-Operating Special Revenue Fund; Not Budgeted; Discretionary)
[4/5 vote required]
body
BACKGROUND
The Public Works Department maintains 420 miles of roads in Napa County. The Napa Valley Wine Train owns and operates the rail system throughout the valley. Where the two systems interconnect there is a shared responsibility for maintaining the roadways where the tracks cross various public roads. The paved area around the tracks that cross Oakville Grade was significantly deteriorated, and the Wine Track had track maintenance to do in the area. We agreed to work together to accomplish both tasks, and to split the costs equally.
The engineer's estimate for the project was $120,000, but through excellent coordination and management the project was completed for $94,416, with the County's share being $47,209 which is eligible for SB-1 funding.
Requested Actions:
1. Approval of Budget Amendment for the following (4/5 vote required):
a. Increase Transfers Out appropriations by $47,209 in the SB-1 Non-Operating Special Revenue Fund (Fund 2440, Sub-Division 1220052, Account 56100) offset by use of its available fund balance to transfer to Project 25032; and
b. Creation of a new Roads Capital Improvement project for the "2025 Oakville Grade Railroad Crossing Repair", RDS 25-101 (Fund 2040, Sub-Division 2040500, Project 25032) and increase Construction Services appropriations by $47,209 (Fund 2040, Sub-Division 2040500, Pro...