Title: Approve and authorize Amendment No. 4 to Agreement No. 230084B with ADKO Engineering, Inc increasing the maximum compensation by $215,975 for a new contract total of $588,781 for additional engineering design and support services; authorize contract change orders to the contract with Bridgeway Civil Constructors Inc.; and approve a Budget Amendment for Annual Guardrails, Project 23006. (Fiscal Impact: $375,000 Expense; SB-1 Non-Operating Special Revenue Fund; Not Budgeted; Discretionary) [4/5 vote required]
Sponsors: Board of Supervisors
Attachments: 1. Agreement, 2. Budget Summary
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TO: Board of Supervisors
FROM: Steven Lederer, Director of Public Works
REPORT BY: Sydney Barclay, Associate Engineer
SUBJECT: Approval of Amendment No. 4 for the PSA with ADKO Engineering; and a Budget Amendment for Chiles Pope Valley Road MPM 3.63 (RDS 22-27) and Silverado Trail at Bell Canyon Creek (RDS 23-37).

RECOMMENDATION
title
Approve and authorize Amendment No. 4 to Agreement No. 230084B with ADKO Engineering, Inc increasing the maximum compensation by $215,975 for a new contract total of $588,781 for additional engineering design and support services; authorize contract change orders to the contract with Bridgeway Civil Constructors Inc.; and approve a Budget Amendment for Annual Guardrails, Project 23006. (Fiscal Impact: $375,000 Expense; SB-1 Non-Operating Special Revenue Fund; Not Budgeted; Discretionary)
[4/5 vote required]
body
BACKGROUND
The Chiles Pope Valley Rd MPM 3.63 Project (RDS 22-27) and Silverado Trail at Bell Canyon Creek Project (RDS 23-37) are two different project activities that are utilizing the same project number, 23006. On August 9, 2022, Napa County entered into Agreement No. 230084B with ADKO to obtain engineering design and consulting services for the Chiles Pope Valley Rd MPM 3.63 and Silverado Trail at Bell Canyon Creek projects. Since the original agreement, the County has issued three (3) amendments to the Agreement due to the evolving scope required for both projects. On June 30, 2024, the Agreement with ADKO Engineering expired; however, work on the above-mentioned projects continues and this Board item is needed to extend the agreement by another two (2) years, increase the maximum compensation under the Agreement, and provide ADKO with necessary funding for construction support to complete these projects. Additionally, this Board Letter requests engineering support budgets for the Chiles Pope Valley Rd MPM 3.63 project and the Silverado Trail at Bell Canyon Creek projects.

The Chiles Pope Valley Rd MPM 3.63 projec...