TO: Board of Supervisors
FROM: David Morrison, Interim County Executive Officer
REPORT BY: Michael Parker, Senior Management Analyst
SUBJECT: ARPA Agreements: Agreement No. 230212B with Napa Sanitation District and Agreement No. 230213B with the City of American Canyon
RECOMMENDATION
title
Interim County Executive Officer requests the following in regards to the American Rescue Plan Act (ARPA):
1. Approval of and authorization for the Chair to sign Agreement No. 230212B with Napa Sanitation District for $1,000,000 towards the design and environmental analysis of a recycled water pump station;
2. Approval of and authorization for the Chair to sign Agreement No. 230213B with the City of American Canyon for $1,500,000 towards the cost of a recycled water system expansion project; and
3. Approval of a Budget Adjustment for the following (4/5 vote required):
a. Increasing appropriations by $2,500,000 in Non-Departmental (Fund 1000, Org 1050000, Acct 54805) offset by the increase in revenue (Transfers In) from American Rescue Plan Act Special Revenue Fund; and
b. Increasing appropriations by $2,500,000 in American Rescue Plan Act Special Revenue Fund Transfer Out Account (Fund 2460, Org 1020050, Acct 56100) offset by use of available fund balance.
body
EXECUTIVE SUMMARY
On August 9, 2022, staff presented two (2) funding requests for Recycled Water Projects from Napa Sanitation District and the City of American Canyon (BOS Item 22-1410). At that meeting, staff recommended allocating $1 million for the design and environmental analysis of a recycled water pump station for Napa Sanitation District, and $1.5 million to the City of American Canyon for a recycled water extension project which was identified in the Napa Valley Drought Contingency Plan to strengthen Napa Valley's long-term water supply reliability and drought resiliency. After the presentation, the Board directed staff to return to a future Board meeting with agreements for both Napa Sanitation District ...