TO: Board of Supervisors
FROM: Steven Lederer, Director of Public Works
REPORT BY: Liang Chin Su, Assistant Engineer
SUBJECT: Approval of Plans and Specifications and Authorization to Advertise for Bids for "East County Roads Paving Project", RDS 25-11
RECOMMENDATION
title
Approve the Plans and Specifications for the "East County Roads Paving Project," RDS 25-11, authorization to advertise for sealed bids and opening of the bids at a time, date, and location to be published by the Director of Public Works pursuant to Section 20150.8 of the Public Contract Code. (No Fiscal Impact; Discretionary)
body
BACKGROUND
The roads to be rehabilitated are selected based on their existing Pavement Condition Index (PCI), which is an overall measure of the condition of the road surface developed by the United Sates Army Corps of Engineers and later standardized by American Society for Testing and Materials (ASTM). The PCI is a numerical index ranging from 0 to 100. Public Works uses the PCI to develop an extended 5-year plan, which is updated annually, to guide our efforts. Please note this is not a "worst first" analysis, it is based on "the best bang for the buck", meaning that smaller amounts of maintenance money on roads that aren't in bad shape can sometimes be much more effectively spent than a large amount of money on a road that has already failed.
The list of roads included in the East County Roads Paving Project include:
* Gordon Valley Road (3 miles - Average PCI of 15)
* Wooden Valley Road MPM 3.75 to 4.75 (1 mile - PCI of 62)
* Wooden Valley Cross Road (1.25 miles - PCI of 27)
* Circle Oaks Drive (1 mile - PCI of 40)
* Sunnyhill Lane (0.4 miles - Average PCI of 27)
Gordon Valley Rd. is funded from the $20 million the Board committed to roads funding in 2021, while the remaining projects are funded from Measure T.
On February 4, 2025 the Board approved the creation of the "East County Roads Paving Project" and a budget transfer of $90,000 ($50,000 from Meas...