Title: Director of Public Works requests the approval of a Budget Transfer for the "Oakville Grade Road Repair", RDS 19-65 Project (4/5 vote required): 1. Increase appropriations by $268,280 in the Accumulated Capital Outlay Fund (ACO) (Fund 3000, Org 3000000, Object 56100) budget with the use of its available fund balance to transfer to Project S9103 (Fund 2040, Org 2040500, Object 48200); and 2. Increase appropriations by $268,280 in Project S9103 (Oakville Grade Road Repair) (Fund 2040, Org 2040500, Object 52360) budget offset by a transfer-in revenue from the ACO budget.
Attachments: 1. Project Budget Summary
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TO: Board of Supervisors
FROM: Steve Lederer - Director of Public Works
REPORT BY: Daniel Basore - Engineering Supervisor
SUBJECT: Budget Transfer for Oakville Grade Road Storm Repair

RECOMMENDATION
title
Director of Public Works requests the approval of a Budget Transfer for the "Oakville Grade Road Repair", RDS 19-65 Project (4/5 vote required):
1. Increase appropriations by $268,280 in the Accumulated Capital Outlay Fund (ACO) (Fund 3000, Org 3000000, Object 56100) budget with the use of its available fund balance to transfer to Project S9103 (Fund 2040, Org 2040500, Object 48200); and
2. Increase appropriations by $268,280 in Project S9103 (Oakville Grade Road Repair) (Fund 2040, Org 2040500, Object 52360) budget offset by a transfer-in revenue from the ACO budget.
body

EXECUTIVE SUMMARY
On August 18, 2020, the Board of Supervisors awarded a Professional Services Agreement (PSA) to MGE Engineering Inc. (MGE) for a maximum of $298,735 for the Oakville Grade Road Repair project.
The preliminary design and engineering phase was completed and approved by FEMA to establish an updated project scope, method of repair and cost to restore the facility back to pre-disaster conditions.
Public Works staff is requesting approval of a budget transfer to fund MGE's Phase 2 Engineering Design services approved under the PSA and for staff time through design and bidding.

FISCAL & STRATEGIC PLAN IMPACT
Is there a Fiscal Impact?
Yes
Is it currently budgeted?
No
Where is it budgeted?
A budget transfer is requested from the Accumulated Capital Outlay (Fund 3000, Org 3000000) by use of its available fund balance.
Is it Mandatory or Discretionary?
Discretionary
Discretionary Justification:
The budget transfer is necessary to move the project to the next Phase and complete Design and Bidding.
Is the general fund affected?
Yes
Future fiscal impact:
Once bids are open a budget transfer will be requested to fund Construction.
Consequences if not approved:
Oakville Grade Road wil...