Skip to main content
Napa County Logo
File #: 25-1140    Version: 1
Type: Agreement Status: Agenda Ready
File created: 6/9/2025 In control: Board of Supervisors
On agenda: 6/24/2025 Final action:
Title: Award of Construction Contract to Team Ghilotti, Inc., of Petaluma, CA in the amount of $4,397,141 for the "Bale, Big Ranch, Lodi, Silverado Trail, and West Zinfandel Paving Project," RDS 25-06; and approve a Budget Amendment. (Fiscal Impact $5,996,147 Expense; Measure T Special Revenue; Not Budgeted; Discretionary) [4/5 vote required]
Sponsors: Board of Supervisors
Attachments: 1. List of Bids, 2. Budget Summary
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TO: Board of Supervisors
FROM: Steven Lederer, Director of Public Works
REPORT BY: Daniel Basore, Engineering Supervisor
SUBJECT: Construction Contract Award and Budget Amendment for the "Bale, Big Ranch, Lodi, Silverado Trail, and West Zinfandel Paving Project," RDS 25-06

RECOMMENDATION
title
Award of Construction Contract to Team Ghilotti, Inc., of Petaluma, CA in the amount of $4,397,141 for the "Bale, Big Ranch, Lodi, Silverado Trail, and West Zinfandel Paving Project," RDS 25-06; and approve a Budget Amendment. (Fiscal Impact $5,996,147 Expense; Measure T Special Revenue; Not Budgeted; Discretionary)
[4/5 vote required]
body
BACKGROUND
On April 22, 2025, the Board of Supervisors (BOS) authorized creation of the "Bale, Big Ranch, Lodi, Silverado Trail, and West Zinfandel Paving Project," RDS 25-06 and a budget amendment of $50,000 to fund the design of the project.
The roads to be included in the project are as follows:
Bale Lane (0.70 miles) - All
Big Ranch Road (0.7 miles) - Oak Knoll Ave (east) to End
Lodi Lane (0.53 miles) - All
Silverado Trail (2.4 miles) - Zinfandel Lane to 6,000 feet south of the Caltrans SR 128
West Zinfandel Lane (0.56 miles) - All
Total miles: 4.9 miles
On May 6, 2025, the Board of Supervisors approved the plans and specifications and authorized to advertise for sealed bids and opening of the bids pursuant to Section 20150.8 of the Public Contract Code. On June 16, 2025, bids were received and opened. The bid results are attached for reference.
Staff recommends awarding the contract to the lowest responsive bidder, Team Ghilotti, Inc., of Petaluma, CA, for their base bid of $4,397,141. Team Ghilotti's base bid is lower than the engineer's estimate of $5,300,000. The total project cost, including design and engineering, construction, construction management, geotechnical services and contingency, is $6,046,147. The project will be funded by Measure-T.
Team Ghilotti, Inc. is not a local vendor however, the Public Contract Code requ...