TO: Board of Supervisors
FROM: Steven Lederer, Director of Public Works
REPORT BY: Sydney Barclay, Associate Engineer
SUBJECT: Pueblo Area Rehabilitation Project, RDS 26-01, Phase II – Approval of the Reimbursement Agreement with the Napa Sanitation District
/
RECOMMENDATION
title
Approve and authorize Agreement No. 270182B with the Napa Sanitation District to reimburse the District for construction costs and District administrative expenses for the “Pueblo Area Rehabilitation Project – Phase 2,” RDS 26-01. (Fiscal Impact $3,000,000 Expense; Local Transportation Tax (T/U); Reallocation of Budget; Discretionary)
body
BACKGROUND
The Napa Sanitation District (NSD) is partnering with the City of Napa and County of Napa to administer the Pueblo Area Rehabilitation Project, which is located in northwest Napa between West Pueblo Avenue, Solano Avenue, Linda Vista Avenue, and Redwood Road. The project was divided into two (2) phases with Phase 1 undergoing construction activities in the north portion of the project limits in 2026, and with plans for Phase 2 to undergo construction improvements in the south half of the project area in 2027. This project will rehabilitate the existing sewer infrastructure, update select City fire hydrants, restore the pavement surface, and repair damaged concrete drainage facilities as needed, among other project related improvements.
Given the expense, vast scope, and available fiscal funding for each agency involved, the project was split into two phases. Phase 1 focused on repairs to the project area north of Janette Drive, south of Redwood Road, east of Linda Vista Avenue, and west of Solano Avenue, and construction is ongoing. Phase 2 would repair the sections of road north of Morlan Drive, south of Janette Drive, east of Rancho Drive, and west of Solano Avenue in 2027.
On May 20, 2025, the Board of Supervisors approved a Professional Services Agreement with Nichols Consulting Engineers, Inc. to prepare Plans and Specifications ...