TO: Board of Supervisors
FROM: Steve Lederer, Director of Public Works
REPORT BY: Liang Chin Su, Assistant Engineer
SUBJECT: Award of Construction Contract for the "Napa Library Building Maintenance Project," PW 25-13A


RECOMMENDATION
title
Award of Construction Contract to CRE Construction Group, Inc. of Granite Bay, California in the amount of $238,663 for the "Napa Library Building Maintenance Project," PW 25-13A. (Fiscal Impact: $238,663, Library Fund; Budgeted; Discretionary)
body
BACKGROUND
The Napa County Library Main Branch was the result of the efforts of a group of 19th-century young men who called themselves "The Excelsior Club." They developed a small collection over the years to serve the Napa community, and that collection was taken over by the City of Napa in 1885. In 1901, George E Goodman donated a building for housing the library-the Goodman Library-which served the citizens of Napa for 60 years.?In 1916, the State of California passed legislation that allowed counties to establish free public libraries, and the Napa County Board of Supervisors then established the Napa County Free Library, located just three blocks from the Goodman Library in downtown Napa. In 1963, the Napa City Library merged with the Napa County Free Library. To better serve the growing service area, and with a combination of funds from the library, the Friends of the Library, and federal and local grants, the current library on Coombs Street was built in 1974 and expanded in the 1990s.?Overall, the facility functions well but shows signs of paint failure, efflorescence at the concrete head of windows (indicating moisture), and minor concrete cracking.
On February 4, 2025 the Board authorized a professional services agreement with Nacht & Lewis Architects, Inc., who was selected in 2022 through 2027 for on-call architectural services, for a not to exceed maximum of $309,800 (this amount included design for the Fifth Street Parking Garage but that project will be bid sepa...