Legislation Details

File #: 24-783    Version: 1
Type: Report Status: Agenda Ready
File created: 4/29/2024 In control: Napa-Vallejo Waste Management Authority
On agenda: 5/9/2024 Final action: 12/31/2023
Title: REQUESTED ACTION: Approval and authorization for the Chair to sign the First Amendment for Agreement 2023-02 with Sonoma RSA, Inc. DBA RSA+, for engineering, architectural and related services to support design and construction of the C&D Building at the Devlin Road Transfer Station, Project #17810 in an amount not to exceed $2,220,000.
Attachments: 1. First Amendment
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

 

TO:                     Napa-Vallejo Waste Management Authority

FROM:                     Chris Celsi, Executive Director

REPORT BY:                     Chris Celsi, Executive Director

SUBJECT:                     First Amendment - Agreement 2023-02 Services to DRTS C&D Building

RECOMMENDATION

title

REQUESTED ACTION: Approval and authorization for the Chair to sign the First Amendment for Agreement 2023-02 with Sonoma RSA, Inc. DBA RSA+, for engineering, architectural and related services to support design and construction of the C&D Building at the Devlin Road Transfer Station, Project #17810 in an amount not to exceed $2,220,000.

body

 

EXECUTIVE SUMMARY

The proposed contract with RSA+ will continue to provide engineering, architectural and related services to support design and construction of the Devlin Road Transfer Station C&D Building, Project #17810. On February 22, 2022 the Authority issued a “Request for Statements of Qualifications for Design and Construction Support for a Building for Processing Construction and Demolition (C&D) Waste.” Statements of qualification were received from three firms on March 25, 2022, and were evaluated by a selection committee. Interviews were conducted with the two highest rated firms. RSA+ received the highest rating from the committee and was selected to enter contract negotiations.

The proposed contract will provide services in three principal phases:
Phase 1. Planning/Updated Opinion of Probable Costs/Schematic Design/Entitlement (not to exceed $445,000)
Phase 2. Design Development (Not to exceed $775,000)
Phase 3. Construction Documents and Bidding (Not to exceed $1,000,000)

FISCAL & STRATEGIC PLAN IMPACT

Is there a Fiscal Impact?

No

 

ENVIRONMENTAL IMPACT

ENVIRONMENTAL DETERMINATION: The proposed action is not a project as defined by 14 California Code of Regulations 15378 (State CEQA Guidelines) and therefore CEQA is not applicable.