Skip to main content
Napa County Logo
File #: 25-1700    Version: 1
Type: Report Status: Agenda Ready
File created: 9/19/2025 In control: Board of Supervisors
On agenda: 10/21/2025 Final action:
Title: Approve and authorize the creation of Project 26015 for the "2026 Annual Guardrail Repair, RDS 26-12"; and approve a Budget Amendment. (Fiscal impact: $110,000, SB-1 Fund; Not Budgeted; Discretionary) [4/5 vote required]
Sponsors: Board of Supervisors
Attachments: 1. Budget Summary
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TO: Board of Supervisors
FROM: Steven Lederer, Director of Public Works
REPORT BY: Dewey Phan, Assistant Engineer
SUBJECT: Project Creation and Budget Amendment for the "2026 Annual Guardrail Repair, RDS 26-12"


RECOMMENDATION
title
Approve and authorize the creation of Project 26015 for the "2026 Annual Guardrail Repair, RDS 26-12"; and approve a Budget Amendment. (Fiscal impact: $110,000, SB-1 Fund; Not Budgeted; Discretionary)
[4/5 vote required]
body

BACKGROUND
The Public Works Department maintains 420 miles of roads and the County classifies 38 miles as arterial, 109 miles as collector, 259 miles as local, and 8 miles as gravel. The County also maintains about 22 miles of guardrails.
Over many years, the County has constructed guardrails to help prevent drivers from driving into the Napa River, into creeks and down roadway embankments. Every year wayward drivers damage guardrails along County roads and Public Works staff create a list of County roads with damaged guardrail to repair. In the past, County staff have hired contractors to repair individual damaged guardrails or the Public Works Roads Division staff repaired the damage as time and funding allowed. With the advent of funding from SB-1, the County now designates $500,000 per year specifically towards guardrail repairs.
The funding requested for these roadway projects is for the project design and repair of the damaged guardrails. Construction is planned for Summer of 2026. The Director of Public Works recommends the approval for the creation of Project 26015 and the Budget Amendment. Staff will return to the Board of Supervisors at a later date for approval of the Plans and Specifications and request for authorization to advertise for bids.

Requested Actions:
1. Approval of Budget Amendment for the following (4/5 vote required):
a. Increase Transfers Out appropriations by $110,000 in the SB-1 Non-Operating Special Revenue Fund
(Fund 2440, Sub-Division 1220052, Account 56100) offse...