Skip to main content
Napa County Logo
File #: 23-1508    Version: 1
Type: Agreement Status: Agenda Ready
File created: 8/22/2023 In control: Board of Supervisors
On agenda: 9/12/2023 Final action:
Title: Director of Public Works requests the following actions: 1. Approval of and authorization for the Chair to sign Agreement No. 240148B with the Napa Valley Vine Trail Coalition regarding the design of the Yountville to St. Helena Segment of the Napa Valley Vine Trail; and 2. Authorization to submit an application for an Active Transportation Program (ATP) Cycle 7 grant, and approval of a commitment of $5 million of future County funding no sooner than Fiscal Year 2025-26 for the construction of the Project.
Sponsors: Board of Supervisors
Attachments: 1. Agreement
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
TO: Board of Supervisors
FROM: Steven Lederer, Director of Public Works
REPORT BY: Graham Wadsworth, P. E., Engineering Supervisor
SUBJECT: Approval of Funding Agreement with Napa Valley Vine Trail Coalition for the design of the Napa Valley Vine Trail between Yountville and St. Helena

RECOMMENDATION
title
Director of Public Works requests the following actions:
1. Approval of and authorization for the Chair to sign Agreement No. 240148B with the Napa Valley Vine Trail Coalition regarding the design of the Yountville to St. Helena Segment of the Napa Valley Vine Trail; and
2. Authorization to submit an application for an Active Transportation Program (ATP) Cycle 7 grant, and approval of a commitment of $5 million of future County funding no sooner than Fiscal Year 2025-26 for the construction of the Project.
body
EXECUTIVE SUMMARY
On June 7, 2022, the Board of Supervisors authorized the Director of Public Works to submit an application for an Active Transportation Program (ATP) Cycle 6 grant for the Napa Valley Vine Trail (NVVT) Yountville to St. Helena Segment and committed up to $5 million of County funding for the construction. The County did not receive a grant and the Director is requesting authorization to submit an application for the next cycle of the same program, known as ATP Cycle 7.
Congressman Thompson included $4 million of Community Project Funding in the federal fiscal year 2023-2024 budget for the Napa Valley Vine Trail Coalition (NVVTC) to complete the planning, engineering, and environmental work of over 10 miles of Class 1 and Class III multiuse path between the existing path in Yountville and the path under construction St. Helena.
Because of the federal funding requirements, NVVTC and County staff recommend that the Board approve a Funding Agreement for the County to administer the design and right-of-way acquisition phases of the Project.

FISCAL & STRATEGIC PLAN IMPACT
Is there a Fiscal Impact?
Yes
Is it currently budgeted?
No
Where...

Click here for full text