On agenda: 5/7/2024 Final action: 12/31/2023
Title: Approve a Budget Amendment for the Napa Berryessa Resort Improvement District (NBRID) Woodhaven Sewer Lift Station Project. (Fiscal Impact: $20,000 Expense, NBRID Fund, Not Budgeted; Discretionary) [4/5 vote required]
Sponsors: Napa Berryessa Resort Improvement District
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TO: Members of the Governing Board
FROM: Christopher Silke - District Engineer
REPORT BY: Christopher Silke - District Engineer
SUBJECT: Budget Amendment for the Woodhaven Court Sewer Lift Station Project

RECOMMENDATION
title
Approve a Budget Amendment for the Napa Berryessa Resort Improvement District (NBRID) Woodhaven Sewer Lift Station Project. (Fiscal Impact: $20,000 Expense, NBRID Fund, Not Budgeted; Discretionary)
[4/5 vote required]
body

BACKGROUND
The Woodhaven Court Sewer Lift Station collects raw sewage from properties on Woodhaven Court, and lifts it through a pumped force main to a gravity sewer main on Headlands Drive where the raw sewage is ultimately transported to the sewer treatment plant. The lift station was destroyed by the 2020 LNU Lightning Complex Fire in August 2020.

NBRID was issued a total of $1,656,941 from Golden State Risk Management Authority (GSRMA) to cover damages incurred by the fire. After accounting for fire-related repairs completed after the fire and the design related charges and construction contracts necessary to replace remaining fire-damaged facilities, approximately $94,959 remained of the insurance settlement issued to NBRID as of April 30, 2024. After including the subject Budget Amendment requested today, the remaining balance of the insurance proceeds for NBRID in the 2020 Lightening Fire Complex budget will be $74,959.

The requested Budget Amendment of $20,000 is expected to cover additional Woodhaven Court Sewer Lift Station construction costs incurred due to unforeseen conditions at the project site during installation of the new facility.

Requested Actions:
1. Approve a Budget Amendment for the following:
a. Increase appropriations of $20,000 to Transfer Out in the 2020 Lightening Complex Fund 1000, Subdivision 1058006 from release of restricted fund balance; and
b. Increase appropriations of $20,000 to Construction Services in the NBRID Woodhaven Sewer Lift Station Project Fund 5240, Subdivis...