Title: Approve and authorize Amendment No. 2 to Agreement No. 240051B (FC) with Wetland Construction, Inc., to increase the maximum amount from $150,000 to $250,000 for general maintenance services and approve a budget amendment. (Fiscal Impact: $100,000 Expense; Flood District; Not Budgeted; Discretionary) [4/5 vote required]
Sponsors: Board of Supervisors
Attachments: 1. Agreement
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TO: Napa County Flood Control and Water Conservation District
FROM: CJ DiMaggio – District Manager
REPORT BY: Jeremy Sarrow – Watershed and Flood Control Resources Specialist
SUBJECT: Amendment No. 2 to Agreement No. 240051B (FC) with Wetland Construction, Inc.

/
RECOMMENDATION
title
Approve and authorize Amendment No. 2 to Agreement No. 240051B (FC) with Wetland Construction, Inc., to increase the maximum amount from $150,000 to $250,000 for general maintenance services and approve a budget amendment. (Fiscal Impact: $100,000 Expense; Flood District; Not Budgeted; Discretionary)
[4/5 vote required]
body

BACKGROUND
Wetland Construction provides support to the Napa County Flood Control and Water Conservation District to provide general maintenance and flood season operations services including sediment removal and management, bank stabilization, erosion control, flap gate and culvert repair and replacement, and additional related general engineering and maintenance services. The District is increasing the budget from one year only to ensure that Wetland Construction, Inc. can continue to provide these services in addition to flood season preparedness activities through the remainder of fiscal year 2026-2027.

Requested Actions:
1. Approve and authorize Amendment No. 2 to Agreement No. 240051B (FC) with Wetland Construction, Inc.
2. Approve a Budget Amendment for the following:
a. Increase appropriations by $50,000 in the Flood District - Watershed Projects budget for Landscaping Services (Fund 8000, Sub-Division 8000500, Account 52340) offset by the use of its available fund balance. Total available fund balance remaining after this adjustment is $3,014,126;
b. Increase appropriations by $50,000 in the Flood Projects Maintenance – Measure A budget for Intrafund Transfers-Out (Fund 8000, Sub-Division 8001200, Account 57900) offset by the use of its available fund balance. Total available fund balance remaining after this adjustment is $13,179,719; and
c. Inc...