SUBJECT: Approval of Project Partnership Agreement No. 260135B (FC) and Amendment 3 to the Project Cooperation Agreement No. 260149B (FC) (Formerly No. 66 (FC)) between the Department of the Army and the Napa County Flood Control and Water Conservation District for Construction for the Napa River/Napa Creek Flood Protection Project
RECOMMENDATION
title
Approve and authorize Project Partnership Agreement No. 260135B (FC) and Amendment 3 of the Project Cooperation Agreement No. 260149B (FC) between the Department of the Army and the Napa County Flood Control and Water Conservation District for Construction of the Napa River/Napa Creek Flood Protection Project. (Fiscal Impact: $48,300,000 Revenue; Flood Project Fund; Budgeted; Discretionary)
body
BACKGROUND
The Napa River/Napa Creek Flood Protection Project is a long-term effort to reduce flood risk to the City of Napa while incorporating environmental restoration and recreational enhancements. The Project, authorized by Congress and implemented in partnership with the U.S. Army Corps of Engineers (USACE), combines engineered flood protection measures with environmental sustainability and community improvements.
The District serves as the local sponsor responsible for coordinating with USACE, securing required local cost- share contributions, and ensuring compliance with applicable federal and state requirements. The Project is partially funded by federal appropriations with matching local contributions from the District and other local sources.
The Project Partnership Agreement (PPA) between the Department of the Army and the Napa County Flood Control and Water Conservation District outlines the responsibilities, cost-sharing arrangements, and commitments required to advance the next construction phase of the Napa River/Napa Creek Flood Protection Project. This...