TO: Board of Supervisors
FROM: Steven Lederer, Director of Public Works
REPORT BY: Frank Lucido, Engineering Manager
SUBJECT: Construction Contract Award and Budget Amendment for the "Mount Veeder MPM 5.2 Repair Project", RDS 25-19
RECOMMENDATION
title
Award a Construction Contract to Rehak General Engineering for the Mount Veeder 5.2 project, RDS 25-19 project; and approve a Budget Amendment. (Fiscal Impact: $1,602,701, Expense; General Fund and Capital Improvement Projects Fund; Not Budgeted; Discretionary)
[4/5 vote required]
body
BACKGROUND
A 72-hour storm event on November 20, 2024 resulted in a slide at Mount Veeder Road mile post marker (MPM) 5.2 reducing traffic to a single lane. On February 4, 2025, another series of storms caused additional damage around the County, leading the Board to declare a local emergency on February 18, 2025. Since then, the roadway has started to exhibit cracking between the two slides and the site has essentially become a single large project. On February 18, 2025, the Board approved a $1,000,000 in funding to address the new slide at Mount Veeder MPM 5.25. On February 25, 2025, the Board approved $301,333 for the design of repairs estimated at MPM 5.2. On May 6, 2025, the Mount Veeder 5.2 and Mount Veeder 5.25 projects were combined and the Board approved advertising the single larger project.
Public Works staff opened bids on June 12, 2025, with the results listed below:
Rehak General Engineering, LLC Auberry, CA $1,687,242
Maggiora & Ghilotti, Inc. San Rafael, CA $1,693,669
E.E. Gilbert Construction, Inc. Martinez, CA $1,844,394
Ground Control Inc. San Francisco, CA $1,897,141
Rege Construction, Inc. Cloverdale, CA $1,974,929
Gordon N. Ball, Inc Walnut Creek, CA $2,050,325
Steelhead Constructors JV Redding, CA ...