TO: Board of Supervisors
FROM: Steven Lederer, Director of Public Works
REPORT BY: Juan Arias - Deputy Director of Public Works
SUBJECT: Soscol Ferry Road/Devlin Road Roundabout Project
RECOMMENDATION
title
Approve multiple Purchase and Sale Agreements and Amendments to Agreements; adopt a Resolution approving a loan; and approve a related Budget Amendment for the Soscol Ferry Road/Devlin Road Roundabout Project. (Fiscal Impact: $421,311 Expense; Multiple Funds; Not Budgeted; Discretionary)
[4/5 vote required]
body
BACKGROUND
The Airport Industrial Area Specific Plan (AIASP) (renamed Napa Valley Business Park) was adopted by the Board of Supervisors on July 29, 1986, to provide for the orderly development of the area around Napa County Airport. The Specific Plan recommended the development of a mechanism for sharing the costs of needed road and intersection improvements among all development within the planning area. These improvements include the extension of Devlin Road and capacity/operational improvements at several intersections, as well as the local share of the cost of major improvements to the State Route 29/12/221 (Soscol Junction) and State Route 29/12 (Airport Junction) intersections.
The Traffic Mitigation Fee program was adopted in December 1990 and has been used since that time as the noted cost-sharing mechanism. The fee was established under the authority of Government Code section 66000. The AIASP also includes improvements to the Soscol Ferry Road and Devlin Road intersection.
Significant progress has been made in the design of the Soscol Ferry Road at Devlin Road Intersection Roundabout Project and in the right of way acquisition process and staff anticipates construction of the project will begin by the Spring of 2026. It is necessary to amend the Purchase and Sale Agreement with one property owner and to enter into two new Purchase and Sale Agreements to obtain rights of way and access for two other properties.
On December 15, 2...
Click here for full text