TO: Board of Supervisors
FROM: Jon Gjestvang, Chief Information Officer - Information Technology Services
REPORT BY: Elena Guzm?n, Staff Services Analyst II
SUBJECT: Approve purchase of Capital Assets and Budget Amendment for Dell PowerEdge Servers.
RECOMMENDATION
title
Authorize purchase of capital assets to replace two Dell servers; and approve related Budget Amendment due to the current servers being at end of their support. (Fiscal Impact: $33,000 Expense, ITS Fund, Not Budgeted; Discretionary)
[4/5 Vote Required]
body
BACKGROUND
The County's voice network servers have reached the end of their support and useful life. To continue to support the County's voice network infrastructure, replacement servers are required. If servers are not replaced, the County's voice infrastructure is at greater risk from cyberattacks, and hardware and software failure.
Requested Actions:
1. Approve purchase of capital assets in the amount of $33,000 for two (2) Dell PowerEdge Servers; and
2. Approve budget amendment increasing capital asset appropriations in the Information Technology Services budget (4200002-55400) in the amount of $33,000 using available Fund Balance.
FISCAL IMPACT
Is there a Fiscal Impact?
Yes
Is it currently budgeted?
No
Where is it budgeted?
Not budgeted, will use Information Technology Services - Available Fund Balance Subdivision 4200002, Account 33100.
Is it Mandatory or Discretionary?
Discretionary
Discretionary Justification:
Current servers are no longer supported by the vendor and must be replaced.
Is the general fund affected?
No
Future fiscal impact:
No future fiscal impact beyond the current fiscal year.
Consequences if not approved:
With the current servers no longer supported, they are now obsolete and failure to replace the current servers will put the County's voice infrastructure at great risk of failure and cyberattacks.
ENVIRONMENTAL IMPACT
ENVIRONMENTAL DETERMINATION: The proposed action is not a project as defined by 14 C...