File #: 25-1598    Version: 1
Type: Agreement Status: Agenda Ready
File created: 8/27/2025 In control: Board of Supervisors
On agenda: 9/9/2025 Final action:
Title: Approve and authorize Amendment No. 1 to Agreement No. 250195B with MCK America, Inc., increasing maximum compensation from $49,278 to $107,441 for additional construction management services, approve and authorize Amendment No. 2 to Agreement No. 240127B with Roundtable Technical Resource, LLC. increasing maximum compensation from $145,000 to $234,010 for additional design services; and approve an associated Budget Amendment for Fuel Farm Improvement Project, PW 24-30. (Fiscal Impact $147,173 Expense; Airport Fund; Not Budgeted; Discretionary) [4/5 vote required]
Sponsors: Board of Supervisors
Attachments: 1. Agreement - MCK America, 2. Budget Summary, 3. Agreement - Roundtable
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
TO: Board of Supervisors
FROM: Steven Lederer, Director of Public Works
REPORT BY: Mark Witsoe, Airport Manager
SUBJECT: Approve Amendment No. 1 to Agreement No. 250195B and Amendment No. 2 to Agreement No. 240127B for the Fuel Farm Improvement Project 24032, PW24-30 at the Napa County Airport


RECOMMENDATION
title
Approve and authorize Amendment No. 1 to Agreement No. 250195B with MCK America, Inc., increasing maximum compensation from $49,278 to $107,441 for additional construction management services, approve and authorize Amendment No. 2 to Agreement No. 240127B with Roundtable Technical Resource, LLC. increasing maximum compensation from $145,000 to $234,010 for additional design services; and approve an associated Budget Amendment for Fuel Farm Improvement Project, PW 24-30. (Fiscal Impact $147,173 Expense; Airport Fund; Not Budgeted; Discretionary)
[4/5 vote required]
body

BACKGROUND
The Fuel Farm Improvement Project (24032), supports the bulk storage fueling facility at the Napa County Airport by providing infrastructure improvements to be used by the Airport and by both Fixed Base Operators (FBOs). Improvements to date have been mutually beneficial to the FBOs and the Airport and the project costs have been shared - 50% Airport and 50% FBOs.

The proposed amendment to Agreement No. 25019B with MCK America, Inc. will address the added work and resources for the construction change orders that were necessary to address unforeseen conditions and minor revisions to the original project improvements. In addition, the proposed amendments to the agreements with MCK America, Inc. and Roundtable Technical Resource, LLC, Agreement (Nos. 250195B and 240127B, respectively), will provide additional design and construction management services for additional fuel farm improvements that will benefit the Airport, including relocation of the Airport's bulk fuel storage tank currently located at 3030 Airport Road to the centralized fuel farm. The additional design serv...