File #: 25-1424    Version: 1
Type: Agreement Status: Agenda Ready
File created: 7/30/2025 In control: Board of Supervisors
On agenda: 8/19/2025 Final action:
Title: Approve and authorize Agreement No. 250450B with Amizetta Winery and Agreement No. 250451B with Quarry Vineyards, LP; authorize contract change orders to construction contract 250460B with Team Ghilotti, Inc.; and approve a Budget Amendment for the "Bale, Big Ranch, Lodi, Silverado Trail, and West Zinfandel Paving Project," RDS 25-06. (Fiscal Impact $2,661,434 Expense; Measure U Non-Operating Special Revenue Fund, Capital Improvement Projects Fund, and Winery Contributions; Not Budgeted; Discretionary) [4/5 vote required]
Sponsors: Board of Supervisors
Attachments: 1. Amizetta Winery Agreement, 2. Quarry Vineyards Agreement, 3. Budget Summary
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TO: Board of Supervisors
FROM: Steven Lederer, Director of Public Works
REPORT BY: Daniel Basore, Engineering Supervisor
SUBJECT: Approval of Agreement No. 250450B with Amizetta Winery and Agreement No. 250451B with Quarry Vineyards, LP, authorize contract change orders to construction contract 250460B with Team Ghilotti, Inc., and a budget amendment for the "Bale, Big Ranch, Lodi, Silverado Trail, and West Zinfandel Paving Project," RDS 25-06.

RECOMMENDATION
title
Approve and authorize Agreement No. 250450B with Amizetta Winery and Agreement No. 250451B with Quarry Vineyards, LP; authorize contract change orders to construction contract 250460B with Team Ghilotti, Inc.; and approve a Budget Amendment for the "Bale, Big Ranch, Lodi, Silverado Trail, and West Zinfandel Paving Project," RDS 25-06. (Fiscal Impact $2,661,434 Expense; Measure U Non-Operating Special Revenue Fund, Capital Improvement Projects Fund, and Winery Contributions; Not Budgeted; Discretionary)
[4/5 vote required]
body
BACKGROUND
On April 22, 2025, the Board of Supervisors (BOS) authorized creation of the "Bale, Big Ranch, Lodi, Silverado Trail, and West Zinfandel Paving Project," RDS 25-06 and a budget amendment of $50,000 to fund the design of the project.

The roads included in the project are as follows:
Bale Lane (0.70 miles) - All
Big Ranch Road (0.7 miles) - Oak Knoll Ave (east) to End
Lodi Lane (0.53 miles) - All
Silverado Trail (2.4 miles) - Zinfandel Lane to 6,000 feet south of the Caltrans SR 128 Right of Way
West Zinfandel Lane (0.56 miles) - All
Total miles: 4.9 miles

On May 6, 2025, the Board of Supervisors approved the plans and specifications and authorized to advertise for
sealed bids and opening of the bids pursuant to Section 20150.8 of the Public Contract Code.

On June 24, 2025 The Board of Supervisors awarded the contract to the lowest responsive bidder, Team Ghilotti, Inc., of Petaluma, CA, for their base bid of $4,397,141.

Amizetta Winery (also known as William Ha...