Napa County Logo
File #: 24-980    Version: 1
Type: Report Status: Agenda Ready
File created: 5/23/2024 In control: Flood Control and Water Conservation District
On agenda: 7/16/2024 Final action:
Title: Approve Purchase and Sale Agreement 250012B (FC) for the full acquisition of fee title of property located at 501 North Bay Drive (APN 044-220-017), Napa, California, owned by Enzo Orciuoli at a price of $675,000.00. (Fiscal Impact: $675,000 Expense; Flood Projects; Budgeted; Discretionary)
Sponsors: Board of Supervisors
Attachments: 1. Agreement
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TO: Napa County Flood Control and Water Conservation District
FROM: Richard Thomasser - District Manager
REPORT BY: Andrew Butler - District Engineer
SUBJECT: Approve a Purchase and Sale Agreement 250012B (FC)

RECOMMENDATION
title
Approve Purchase and Sale Agreement 250012B (FC) for the full acquisition of fee title of property located at 501 North Bay Drive (APN 044-220-017), Napa, California, owned by Enzo Orciuoli at a price of $675,000.00. (Fiscal Impact: $675,000 Expense; Flood Projects; Budgeted; Discretionary)
body

BACKGROUND
The Napa River/Napa Creek Flood Protection Project covers 6.9 miles of the Napa River, as well as 0.6 miles of the Napa Creek. Components of this project include widening the river channel through the creation of both marsh plain and floodplain terraces adjacent to the river, replacing several bridges, including the railroad bridge over the Napa River, and the creation of a bypass channel through downtown Napa. The overall project requires the acquisition of property interests on approximately 300 parcels of land.

The Floodwalls North of the Bypass Project (Project), the next phase of the larger Napa River/Napa Creek Flood Protection Project, extends approximately 1 mile along the west bank of the Napa River from the River Terrace Inn on the south end to the Elks Grove Townhomes to the north. Major components of the Project include a setback concrete or sheet pile floodwall along the bank of the river, improved scour protection under the Lincoln Ave bridge, completing the floodwall on the north side of the dry bypass channel, and construction of a public trail south of Lincoln Avenue that will connect the existing Napa River trail to the Oxbow Commons including a new pedestrian crossing of Lincoln Avenue. This phase of the Project requires acquisition of easements or fee title on approximately 45 parcels in the City of Napa.

The subject of this item, the required property rights proposed for acquisition at 501 North Bay Drive,...