File #: 22-2032    Version: 1
Type: Agreement Status: Agenda Ready
File created: 10/27/2022 In control: Board of Supervisors
On agenda: 11/8/2022 Final action: 12/31/2023
Title: Interim County Executive Officer requests the following in regards to the American Rescue Plan Act (ARPA): 1. Approval of and authorization for the Chair to sign Agreement No. 230212B with Napa Sanitation District for $1,000,000 towards the design and environmental analysis of a recycled water pump station; 2. Approval of and authorization for the Chair to sign Agreement No. 230213B with the City of American Canyon for $1,500,000 towards the cost of a recycled water system expansion project; and 3. Approval of a Budget Adjustment for the following (4/5 vote required): a. Increasing appropriations by $2,500,000 in Non-Departmental (Fund 1000, Org 1050000, Acct 54805) offset by the increase in revenue (Transfers In) from American Rescue Plan Act Special Revenue Fund; and b. Increasing appropriations by $2,500,000 in American Rescue Plan Act Special Revenue Fund Transfer Out Account (Fund 2460, Org 1020050, Acct 56100) offset by use of available fund balance.
Attachments: 1. Agreement - Napa Sanitation District, 2. Agreement - City of American Canyon, 3. 22-2032 Board Letter
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

 

TO:                     Board of Supervisors

FROM:                     David Morrison, Interim County Executive Officer

REPORT BY:                     Michael Parker, Senior Management Analyst

SUBJECT:                     ARPA Agreements: Agreement No. 230212B with Napa Sanitation District and Agreement No. 230213B with the City of American Canyon

 

RECOMMENDATION

title

Interim County Executive Officer requests the following in regards to the American Rescue Plan Act (ARPA):
1. Approval of and authorization for the Chair to sign Agreement No. 230212B with Napa Sanitation District for $1,000,000 towards the design and environmental analysis of a recycled water pump station;
2. Approval of and authorization for the Chair to sign Agreement No. 230213B with the City of American Canyon for $1,500,000 towards the cost of a recycled water system expansion project; and
3. Approval of a Budget Adjustment for the following (4/5 vote required):
a. Increasing appropriations by $2,500,000 in Non-Departmental (Fund 1000, Org 1050000, Acct 54805) offset by the increase in revenue (Transfers In) from American Rescue Plan Act Special Revenue Fund; and
b. Increasing appropriations by $2,500,000 in American Rescue Plan Act Special Revenue Fund Transfer Out Account (Fund 2460, Org 1020050, Acct 56100) offset by use of available fund balance.

body

 

EXECUTIVE SUMMARY

On August 9, 2022, staff presented two (2) funding requests for Recycled Water Projects from Napa Sanitation District and the City of American Canyon (BOS Item 22-1410). At that meeting, staff recommended allocating $1 million for the design and environmental analysis of a recycled water pump station for Napa Sanitation District, and $1.5 million to the City of American Canyon for a recycled water extension project which was identified in the Napa Valley Drought Contingency Plan to strengthen Napa Valley’s long-term water supply reliability and drought resiliency. After the presentation, the Board directed staff to return to a future Board meeting with agreements for both Napa Sanitation District and the City of American Canyon in order to fund the aforementioned proposals.

Today’s requested action is for approval of and authorization for the Chair to sign both Agreement No. 230213B with the City of American Canyon for $1,500,000 towards the cost of a recycled water system expansion project, Agreement No. 230212B with Napa Sanitation District for $1,000,000 towards the design and environmental analysis of a recycled water pump station, as well as approval of a corresponding budget transfer in the amount of $2,500,000 to fund both agreements. 

 

FISCAL & STRATEGIC PLAN IMPACT

Is there a Fiscal Impact?

Yes

Is it currently budgeted?

Yes

Where is it budgeted?

American Rescue Plan Act funds (Fund 2460, Org 102005)

Is it Mandatory or Discretionary?

Discretionary

Discretionary Justification:

Utilization of Grant Funds

Is the general fund affected?

Yes

Future fiscal impact:

None; this is use of one time monies

Consequences if not approved:

None; monies will be appropriated for other eligible uses

County Strategic Plan pillar addressed:

Livable Economy for All

 

ENVIRONMENTAL IMPACT

ENVIRONMENTAL DETERMINATION: The proposed action is not a project as defined by 14 California Code of Regulations 15378 (State CEQA Guidelines) and therefore CEQA is not applicable.

 

BACKGROUND AND DISCUSSION

The American Rescue Plan Act provides funding needed for state and local governments to respond to the COVID-19 public health emergency and lead a strong, resilient, and equitable recovery.  In May 2021, Napa County received a federal grant allocation totaling $26.76 million, and continues to evaluate how to provide for its local public health and economic recovery responses. At the direction of the Board, staff’s current strategy is to make use of ARPA monies in the areas of public health, community investment to address economic impacts resulting from COVID-19, and infrastructure.

On August 9, 2022, staff, with the support of the Acting County Executive Officer and Director of Public Works, presented two (2) funding requests for Recycled Water Projects from Napa Sanitation District and the City of American Canyon using Napa County’s allocation of ARPA monies under the ARPA Infrastructure Category (BOS Item 22-1410). Under ARPA’s Infrastructure Category, the Board previously approved $1,350,000 for water and wastewater improvement projects at the Lake Berryessa Resort Improvement District, and $375,000 for a Broadband Project Manager for the two and a half remaining years of ARPA eligible expenditures. 

Napa Sanitation’s Recycled Water Pump Station Project Proposal is as follows:

NapaSan operates a recycled water pump station at the wastewater treatment plant. Tertiary treated and disinfected recycled water is stored in two reservoirs. Water from these reservoirs is pumped into the recycled water distribution system for delivery to customers. The station consists of three large (600 hp) pumps, one small pump, valves, flow meters, and electrical and controls equipment.

The recycled water distribution system is separated into north and south systems. The north distribution system serves areas north of the treatment plant including Kennedy Park, Napa Valley College, and the Coombsville Area. The south distribution system provides recycled water to areas south, east, and west of the treatment plant including the Carneros area, Eagle Vines/Chardonnay golf course, and the Airport industrial area. Flow and pressure to the north system is provided by one large pump and one small pump. South system flow and pressure is provided by one large pump. The third large pump can provide additional pumping capacity to the north or south system during peak demand periods. A fourth large pump is needed because peak demands can occur on the north and south systems simultaneously.

Additionally, a lack of redundancy exists and is problematic when one of the large pumps is out of service for either the north or south branch. Due to the complexity of completing repairs, outages can last longer than anticipated. Since the spare large pump is common to both branches, the station has less capacity during a large pump outage which limits its ability to meet customers’ needs.

The recycled water pump station upgrade and modification is needed to address pressure, reliability, and redundancy issues while maintaining separation between the north and south distribution systems. The proposed pump station upgrade project would include one large and one small pump on the south distribution side. The proposed configuration would provide large pumps for peak demands and small pumps to prolong the life of the large pumps and conserve energy during periods of lesser demand.

NapaSan is in the final stage of a two-year comprehensive planning document which evaluates wastewater treatment plant capacity, recycled water production capacity, condition assessment, capital project needs, and recycled water supply through the year 2040. Several recycled water projects are analyzed, including additional recycled water daily storage, additional recycled water treatment filtration, and recycled water pumping. Of the projects reviewed, recycled water pump station reliability and redundancy improvements is the most needed in the short term.

The comprehensive planning document confirms that NapaSan’s recycled water supply is limited. Annual supply is less than anticipated in previous studies due to in-home water conservation measures by customers within NapaSan’s sewer service area. Less wastewater results in a lower recycled water supply. It is anticipated that the demand for recycled water by existing customers and by properties located adjacent or near the existing recycled water pipeline could reach or exceed NapaSan’s recycled water supply. If this is true, additional recycled water pipelines are not prioritized.

NapaSan recommends that the pump station project is the highest priority for recycled water funding. This project would benefit all of NapaSan’s recycled water customers and provide additional drought resilience by increasing the reliability of recycled water delivery.

The City of American Canyon’s Recycled Water System Expansion Project Proposal is as follows:

Background: Napa County (County) and the City of American Canyon (City) are contractors of the California State Water Project and are seeking to reduce dependence on a non-local, overallocated source of water - the Sacramento-San Joaquin River Delta. The City and County are participating agencies of the North Bay Water Reuse Authority’s (NBWRA) Phase 2 Program which is a regional initiative aimed at increasing the North Bay’s water supply reliability and resiliency with recycled water.

The City has been in a Stage 2 Drought Emergency since July 2021 and is planning to implement a portion of its Phase 1 Recycled Water Distribution System Expansion, which is scoped in the NBWRA Phase 2 Program, to offset potable water demand. During the Stage 2 Drought Emergency all potable water customers are subject to a 20% reduction in water use with additional restrictions possible as the drought continues.

The corresponding City project, known as the Recycled Water System Expansion Project (RW17- 0100) (Project) is anticipated to provide an annual benefit of 69 acre-feet in potable water use offset (including 37 acre-feet used in the County), based on a three-year average.

The 37 acre-feet of potable water used in the County equates to 16 County industrial businesses that would benefit from the Project including the Napa Recycling and Compost Facility. In addition, the Project may improve the ability for additional County development within this area as the required extension of this portion of recycled pipeline has been cost prohibitive to County applicants.

Project description: The City of American Canyon (American Canyon) identified several pipeline extensions of the existing system to deliver recycled water to existing landscaping and industrial users on potable water and convert them to recycled water for non-potable uses. The customer demands associated with these extensions would be met directly from the Water Reclamation Facility (WRF) during the peak months. No seasonal storage would be needed. The recycled water project being implemented at this time is located within existing built roadways. These pipeline extensions are described below:

•                     The construction of approximately 5,280 LF of 12-inch recycled water pipelines along Devlin Road and Tower Road. The limits include: Devlin Road between South Kelly Road and Tower Road and Tower Road between the Tower Road cul-de-sac and Highway 29. These pipelines connect to the existing 12-inch pipelines in Devlin Road. These pipelines will help offset potable water demands from customers in those areas by converting all of their irrigation and some of their industrial water use to recycled water.

•                     The construction of approximately 2,443 LF of 8-inch diameter recycled water pipelines along Hess Drive and Lombard Road which will offset potable water demands from customers in those areas by converting all of their irrigation and some of their industrial water use to recycled water.

•                     The construction of approximately 1,553 LF of 6-inch diameter recycled water pipelines in Spikerush Circle to convert irrigation of American Canyon Community Park from potable water to recycled water.

•                     The construction of approximately 2,413 LF of 6-inch diameter recycled water pipelines in Benton Way to convert irrigation demands at the middle school, community services, and park from potable water to recycled water.

The Project components for American Canyon’s Phase 1 Recycled Water Distribution System Expansion include the following:

•                     Major Facilities: 5,280 LF of 12-inch-diameter pipelines, 2,443 LF of 8-inch-diameter pipelines, and 3,966 LF of 6-inch-diameter pipelines.

•                     Project Yield: 69 AFY (37 AFY in County)

•                     Total Project Capital Cost: $3.5 million.

•                     Annual O&M Cost: $22,000, based on additional labor to maintain and repair the pipelines.

This project would efficiently utilize existing assets to increase the distribution of recycled water. Pipeline projects such as this have low vulnerability to climate change because these projects generally involve constructing buried, pressurized pipelines; however, water quality and quantity conveyed by the pipeline could be impacted by quality changes at the American Canyon WRF. Material selection for the pipelines and fittings should take into consideration the possibility of corrosion from seawater as well as other typical and site-specific parameters.

Improving Water Supply Reliability and Sustainability
For American Canyon, the Phase 1 Recycled Water Distribution System Expansion will convert existing landscaping and industrial users on potable water to recycled water for non-potable uses. Like Napa County, American Canyon is a contractor on the California State Water Project (SWP), which would reduce dependence on a non-local, overallocated source of water - the Sacramento-San Joaquin River Delta. The development of local supplies, such as recycled water, helps keep water importers from seeking additional water from the Delta.

Over the last couple of years, the drought conditions in the region have highlighted the heavy stresses most regional water sources (i.e., surface flow, groundwater and imported water) are under. Projects like these will reduce stresses on limited water supplies by providing tertiary treated recycled water for urban, environmental and agricultural irrigation users. Without this new supply of recycled water to meet demands, overuse of existing supply will continue, leading to long-term detrimental impacts to streamflow and the riparian and aquatic habitat it supports, groundwater aquifers resulting in increased salinity and sea-water intrusion, water quality degradation, and low pumping levels. For these reasons, this project was identified in the Napa Valley Drought Contingency Plan as one of the projects that would help to strengthen Napa Valley’s long-term water supply reliability and drought resilience.

Recommendation and Requested Action

Staff recommends awarding $1,000,000 to Napa Sanitation District to fund the design and environmental analysis of their recycled water pump station project. Funding the design and environmental analysis of the project will be executed within ARPA timelines and the project will help ensure availability of recycled water to many existing and future customers.

Staff also recommends awarding $1,500,000 to the City of American Canyon to fund its recycled water extension project. The project will move several users off of groundwater, including some customers in the unincorporated County.  Additionally, the project is shovel ready, and with the ARPA contribution included, fully funded.

Today’s requested action is for the following:

1. Approval of and authorization for the Chair to sign Agreement No. 230212B with Napa Sanitation District for $1,000,000 towards the design and environmental analysis of a recycled water pump station;

2. Approval of and authorization for the Chair to sign Agreement No. 230213B with the City of American Canyon for $1,500,000 towards the cost of a recycled water system expansion project; and

3. A budget adjustment:

a. Increasing appropriations by $2,500,000 in Non-Departmental (Fund 1000, Org 1050000, Acct 54805) offset by the increase in revenue (Transfers In) from American Rescue Plan Act Special Revenue Fund; and

b. Increasing appropriations by $2,500,000 in American Rescue Plan Act Special Revenue Fund Transfer Out Account (Fund 2460, Org 1020050, Acct 56100) offset by use of available fund balance (4/5 vote required).