Skip to main content
Napa County Logo
File #: 22-746    Version: 1
Type: Report Status: Agenda Ready
File created: 4/5/2022 In control: Board of Supervisors
On agenda: 4/19/2022 Final action: 12/31/2023
Title: Director of Public Works requests approval of plans and specifications for "East Central Paving Project, Phase Two," RDS 21-25B, authorization to advertise for sealed bids, and opening of the bids at a time, date and location to be published by the Director of Public Works pursuant to Section 20150.8 of the Public Contract Code.
Sponsors: Board of Supervisors
Attachments: 1. Budget
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

 

TO:                     Board of Supervisors

FROM:                     Steven Lederer, Director of Public Works

REPORT BY:                     Liang Chin Su, Assistant Engineer

SUBJECT:                                          Approval of Plans and Specifications and Authorization to Advertise for Bids for “East Central Paving Project, Phase Two”. RDS 21-25B

 

RECOMMENDATION

title

Director of Public Works requests approval of plans and specifications for "East Central Paving Project, Phase Two," RDS 21-25B, authorization to advertise for sealed bids, and opening of the bids at a time, date and location to be published by the Director of Public Works pursuant to Section 20150.8 of the Public Contract Code.

body

EXECUTIVE SUMMARY

The County has received funds from Pacific Gas and Electric (PG&E) as a settlement for damages caused by the 2017 North Bay fires. The Board has designated $16 million of this funding towards road repairs. On May 4, 2021, the Board of Supervisor authorized $5,250,000 in funding to conduct repairs for East Central Paving Project Phase One, which was completed during FY 21-22. The remainder of Phase One funding and an anticipated additional $1,500,000 from PG&E funds will be used to conduct repairs for East Central Paving Project Phase Two, which includes the following roads:

                     Second Avenue (All - southbound lane)

                     Vichy Avenue (All)

                     Mt. George Avenue (All)

                     Olive Hill Lane (All)

The Director of Public Works recommends approval of plans and specifications and authorization to put the project out to bid in order to move into the construction phase of the project.

FISCAL & STRATEGIC PLAN IMPACT

Is there a Fiscal Impact?

No

Is it currently budgeted?

Yes

Where is it budgeted?

Fund 2040, Org 2040500, Project 21067

Is it Mandatory or Discretionary?

Discretionary

Discretionary Justification:

Approval of plans and specifications and authorization to advertise for sealed bids is necessary to move to the construction phase.

Is the general fund affected?

No

Future fiscal impact:

Staff will return and request the additional funds required to fund the project at the time of the construction contract award.

Consequences if not approved:

The project will not move forward to the construction phase and the damaged roads will not be repaired.

County Strategic Plan pillar addressed:

Livable Economy for All

 

ENVIRONMENTAL IMPACT

ENVIRONMENTAL DETERMINATION: Consideration and possible adoption of a Categorical Exemption Class 1: It has been determined that this type of project does not have a significant effect on the environment and is exempt from the California Environmental Quality Act. [See Class 1 (“Existing Facilities”) which may be found in the guidelines for the implementation of the California Environmental Quality Act at 14 CCR §15301; see also Napa County’s Local Procedures for Implementing the California Environmental Quality Act, Appendix B.]

BACKGROUND AND DISCUSSION

Napa County has settled with PG&E and recovered $33,954,044 to compensate the County for roadway damages, response costs and lost revenue funds that resulted from the 2017 North Bay fires. On July 28, 2020, the Board of Supervisors (Board) allocated $16,000,000 of this settlement to repair roadway damages. On May 4, 2021, the Board authorized an increase in the revenue and expenditures of $5,250,000 for a project to repair the following damaged roads:

                     Atlas Peak Road (2400 feet North of Hardman Avenue to Westgate Drive)

                     Hillcrest Avenue (All)

                     Westgate Avenue (All)

                     Soda Canyon Road (Silverado Trail to Loma Vista Drive)

                     Second Avenue (All - northbound lane)

                     Maui Way (All)

                     Pinnacle Peak (All)

After the completion of East Central Paving Project Phase One, approximately $1,600,000 remained from the appropriated amount. Pending bid results, the remaining funds from Phase One and an anticipated request for additional $1,500,000 will be used to repair the following roads as part of the East Central Paving Project, Phase Two:

                     Second Avenue (All - southbound lane)

                     Vichy Avenue (All)

                     Mt. George Avenue (All)

                     Olive Hill Lane (All)

Approval of this item will allow the project to move toward the construction phase to repair the damaged roads. Proposed road treatments consist of grind and overlays, dig out and repairing failed areas, striping, and signage. Project construction is anticipated in summer of 2022. The estimated total project cost for East Central Paving Project, Phase Two is $3,100,000. Staff will return to the Board later to present a detailed project budget and for award of a construction contract after bids are opened.