Legislation Details

File #: 22-1962    Version: 1
Type: Agreement Status: Agenda Ready
File created: 10/15/2022 In control: Board of Supervisors
On agenda: 11/8/2022 Final action: 12/31/2023
Title: Director of Public Works requests the following approvals related to easements necessary for the Dry Creek Road Bridge over Dry Creek Replacement Project, RDS 15-22: 1. Approval and authorization for the Chair to sign a Purchase and Sale Agreement No. 230231B with Shai Shefer, a married man as his sole and separate property and Gil Shefer, an unmarried man as Joint Tenants, for the value of $559,000 (Assessor's Parcel Number 027-330-002); and 2. Approval of a Budget Transfer for the following (4/5 vote required): a. Increase appropriations by $200,000 in the Accumulated Capital Outlay (ACO) Fund (Fund 3000, Org 3000000) to transfer to Project 14009 (Fund 2040, Org 2040500) offset by use of its available fund balance; and b. Increase appropriations by $200,000 in the Project 14009 budget offset by a transfer-in revenue from the ACO.
Attachments: 1. Budget Summary, 2. Agreement, 3. 22-1962 Board Letter
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

 

TO:                     Board of Supervisors

FROM:                     Steven Lederer, Director of Public Works

REPORT BY:                     Graham Wadsworth, Engineering Supervisor

SUBJECT:                     Approval of Purchase and Sale Agreement No. 230231B in support of the Construction of Dry Creek Road Bridge over Dry Creek Replacement Project, RDS 15-22

 

RECOMMENDATION

title

Director of Public Works requests the following approvals related to easements necessary for the Dry Creek Road Bridge over Dry Creek Replacement Project, RDS 15-22:

1.                     Approval and authorization for the Chair to sign a Purchase and Sale Agreement No. 230231B with Shai Shefer, a married man as his sole and separate property and Gil Shefer, an unmarried man as Joint Tenants, for the value of $559,000 (Assessor’s Parcel Number 027-330-002); and

2.                     Approval of a Budget Transfer for the following (4/5 vote required):

a.                     Increase appropriations by $200,000 in the Accumulated Capital Outlay (ACO) Fund (Fund 3000, Org 3000000) to transfer to Project 14009 (Fund 2040, Org 2040500) offset by use of its available fund balance; and

b.                     Increase appropriations by $200,000 in the Project 14009 budget offset by a transfer-in revenue from the ACO.

body

 

EXECUTIVE SUMMARY

The Dry Creek Road Bridge over Dry Creek is over 100 years old and is in need of replacement. Caltrans reported that the bridge is structurally deficient, functionally obsolete and unstable due to scour under the north abutment. Dry Creek Road is designated as a “minor collector”, and the existing bridge is an “Off-System" bridge, and thus the replacement is eligible for 88.53% Highway Bridge Program (HBP) funding and 11.47% Toll Credits as the match for local funds.

On May 9, 2022, Caltrans authorized the County to proceed with the right-of-way (ROW) acquisition phase of the project. During the project design, the consultant determined that constructing the road over the southern portion of the Shefer property rendered the property undevelopable. The property owners purchased the vacant property to build a home; therefore, the County offered to purchase the entire property.

When County staff requested HBP funding, the cost estimate for the property was $345,000, but property values in the area have increased significantly. The right-of-way consultant conducted an appraisal in compliance with Federal Highway Administration procedures and made a $559,000 offer to purchase the entire property. The property owners accepted the offer, County Counsel prepared a purchase and sale agreement, and the property owners signed it. The request for a budget transfer is to provide additional funding to purchase the property.
Our goal is to complete the regulatory permit process and right-of-way acquisitions in 2023 and commence construction in the summer of 2024, so long as HBP construction funds are available. The total cost to complete the right-of-way phase is $750,000. Even though the entire project is reimbursable, Caltrans could determine that some expenses are not eligible for federal funding. Cash Flow funding will be provided by the ACO. After repayments from Caltrans are received, the ACO will be reimbursed. The ACO will be reimbursed with Measure T funds for any expenses that Caltrans determines are not eligible for federal funding.

 

FISCAL & STRATEGIC PLAN IMPACT

Is there a Fiscal Impact?

Yes

Is it currently budgeted?

No

Where is it budgeted?

The project is currently budgeted in Fund 2040, Org 2040500 and Project 14009. The budget transfer will allow the County to use ACO funds to cash flow this phase of the right-of-way acquisitions. As always, we will work to maximize our reimbursement from Caltrans. If Caltrans determines that some expenses are not eligible for reimbursement, then Measure T funds will reimburse the ACO.

Is it Mandatory or Discretionary?

Discretionary

Discretionary Justification:

The property is needed to construct the bridge project. The consultant evaluated two alternatives that were more expensive than the current design.

Is the general fund affected?

No

Future fiscal impact:

The Dry Creek Road Bridge Replacement Project is eligible for 100% Federal and Toll Credit funding; however, some expenses may not be eligible and will be paid for by the Measure T funds. It is anticipated that all the work will be completed in fiscal year 2025-26 however permitting agencies may require future maintenance and monitoring work.

Consequences if not approved:

The County will forfeit Federal Highway Administration HBP grant funds, would not replace the existing bridge, and might be required to return the HBP funding received to date.

County Strategic Plan pillar addressed:

Healthy, Safe, and Welcoming Place to Live, Work, and Visit

Additional Information

In Fiscal Year 2016-17, the Board budgeted $958,420 from the Roads Fund to cash flow the consultant and County staff expenses during design/engineering. Caltrans has reimbursed some funding for design/engineering to date. On July 13, 2021, the Board approved Amendment 1 and a $321,054 budget transfer from the Measure T fund. On December 14, 2021, the Board approved Amendment 2 and a $133,150 budget transfer from the Measure T fund. On June 7, 2022, the Board approved Amendment 3 and a $900,000 budget transfer from the ACO.

 

ENVIRONMENTAL IMPACT

ENVIRONMENTAL DETERMINATION: The proposed action is not a project as defined by 14 California Code of Regulations 15378 (State CEQA Guidelines) and therefore CEQA is not applicable. On February 1, 2022, the Board adopted a Mitigated Negative Declaration for the Project.

 

BACKGROUND AND DISCUSSION

The Napa County Public Works Department is responsible for maintaining 78 bridges that are included in the National Bridge Inventory. The Federal Highway Administration (FHWA) provides Highway Bridge Program (HBP) funding to replace bridges when needed and the State of California Department of Transportation (Caltrans) administers the HBP in California.

On August 20, 2012, Caltrans issued a letter to Cities and Counties requesting local agencies to review their public highway bridges for potential replacement, rehabilitation, or preventive maintenance and to take necessary actions to address any public safety issues and to extend the life of our bridge inventory. County staff evaluated fourteen (14) bridges and prioritized eight (8) bridges for the first phase of the HBP. Caltrans and the FHWA programmed HBP funding to replace seven bridges.

The Dry Creek Road Bridge over Dry Creek (0.8 miles west of Mt. Veeder Rd.) is over 100 years old. Caltrans identified the bridge is structurally deficient, functionally obsolete and unstable due to scour under the north abutment. The substructure of the existing bridge has cracking and weathering of the mortar in the joints of the stone masonry abutments. The top section of the retaining wall near the north abutment has broken away and is leaning outward horizontally. The width is only 18 feet between the barriers, which does not meet the AASHTO standard of 11-foot minimum lanes.

Dry Creek Road is designated as a “minor collector”, and the existing bridge is an “Off-System" bridge, and thus the project is eligible for 88.53% HBP funding and 11.47% Toll Credits funding as the match for local funds. The proposed bridge structure would consist of an approximately 80-foot-long by 32-foot-wide single-span concrete slab bridge on pre-cast and pre-stressed concrete girders. The project also includes 900 feet of new roadway to remove two curves in Dry Creek Road. County staff anticipates that the contractor will build the project in four stages to minimize the disruption to traffic and this would require work in Dry Creek over two summers.

On May 9, 2022, Caltrans authorized the County to proceed with the right-of-way (ROW) acquisition phase of the project. During the project design, the consultant determined that constructing the road over the southern portion of the Shefer property undevelopable. The property owners purchased the vacant property to build a home; therefore, the County offered to purchase the entire property.

When County staff requested HBP funding, the cost estimate for the property was $345,000 but property values in the area have increased significantly. The right-of-way consultant conducted an appraisal in compliance with Federal Highway Administration procedures and made a $559,000 offer to purchase the entire property. The property owners accepted the offer, County Counsel prepared a purchase and sale agreement, and the property owners signed it. The request for a budget transfer is to provide additional funding to purchase the property.

Our goal is to complete the regulatory permit process and right-of-way acquisitions in 2023, and to start construction in the summer of 2024, so long as HBP construction funds are available. The total cost to complete the right-of-way phase is $750,000. Even though the entire project is reimbursable, Caltrans could determine that some expenses are not eligible for federal funding. Cash Flow funding will be provided by the ACO. After repayments from Caltrans are received, the ACO will be reimbursed.