TO: Napa County Legislative Subcommittee
FROM: David Morrison, Interim County Executive Officer
REPORT BY: Jesus Tijero, BOS Staff Assistant II
SUBJECT: SB 706 (Caballero)
RECOMMENDATION
title
Interim County Executive Officer requests discussion and possible action to recommend that the Napa County Board of Supervisors support SB 706 by Senator Caballero.
body
EXECUTIVE SUMMARY
SB 706 (Caballero) Public contracts: progressive design-build: local agencies.
Existing law authorizes the Director of General Services to use the progressive design-build procurement process for the construction of up to 3 capital outlay projects, as jointly determined by the Department of General Services and the Department of Finance, and prescribes that process. Existing law defines “progressive design-build” as a project delivery process in which both the design and construction of a project are procured from a single entity that is selected through a qualifications-based selection at the earliest feasible stage of the project. Existing law, until January 1, 2029, authorizes local agencies, defined as any city, county, city and county, or special district authorized by law to provide for the production, storage, supply, treatment, or distribution of any water from any source, to use the progressive design-build process for up to 15 public works projects in excess of $5,000,000 for each project, similar to the progressive design-build process authorized for use by the Director of General Services. Existing law requires a local agency that uses the progressive design-build process to submit, no later than January 1, 2028, to the appropriate policy and fiscal committees of the Legislature a report on the use of the progressive design-build process containing specified information, including a description of the projects awarded using the progressive design-build process. Existing law requires the design-build entity and its general partners or joint venture members to verify specified information under penalty of perjury. This bill would authorize all cities, counties, city and counties, or special districts to use the progressive design-build process for other projects in addition to water-related projects. The bill would change the required reporting date to no later than December 31, 2028. This bill contains other related provisions and other existing laws.
ENVIRONMENTAL IMPACT
ENVIRONMENTAL DETERMINATION: The proposed action is not a project as defined by 14 California Code of Regulations 15378 (State CEQA Guidelines) and therefore CEQA is not applicable.
BACKGROUND AND DISCUSSION
SB 706 (Caballero) Public contracts: progressive design-build: local agencies.
Existing law authorizes the Director of General Services to use the progressive design-build procurement process for the construction of up to 3 capital outlay projects, as jointly determined by the Department of General Services and the Department of Finance, and prescribes that process. Existing law defines “progressive design-build” as a project delivery process in which both the design and construction of a project are procured from a single entity that is selected through a qualifications-based selection at the earliest feasible stage of the project. Existing law, until January 1, 2029, authorizes local agencies, defined as any city, county, city and county, or special district authorized by law to provide for the production, storage, supply, treatment, or distribution of any water from any source, to use the progressive design-build process for up to 15 public works projects in excess of $5,000,000 for each project, similar to the progressive design-build process authorized for use by the Director of General Services. Existing law requires a local agency that uses the progressive design-build process to submit, no later than January 1, 2028, to the appropriate policy and fiscal committees of the Legislature a report on the use of the progressive design-build process containing specified information, including a description of the projects awarded using the progressive design-build process. Existing law requires the design-build entity and its general partners or joint venture members to verify specified information under penalty of perjury. This bill would authorize all cities, counties, city and counties, or special districts to use the progressive design-build process for other projects in addition to water-related projects. The bill would change the required reporting date to no later than December 31, 2028. This bill contains other related provisions and other existing laws.