Title: Approve a Budget Amendment to increase Maintenance Building & Improvements appropriation by $60,000 in the Property Management Maintenance subdivision offset by use of Appropriation for Contingency for the repair of equipment in the Administration Building ITS Cold Room. (Fiscal Impact: $60,000 Expense; Property Management Fund; Not Budgeted; Discretionary) [4/5 vote required]
Sponsors: Board of Supervisors
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

 

TO:                     Board of Supervisors

FROM:                     Steven Lederer, Director of Public Works

REPORT BY:                     Marcela Aparicio, Supervising Staff Services Analyst

SUBJECT:                     Budget Amendment for repair to equipment in the Administration Building ITS Cold Room.

RECOMMENDATION

title

Approve a Budget Amendment to increase Maintenance Building & Improvements appropriation by $60,000 in the Property Management Maintenance subdivision offset by use of Appropriation for Contingency for the repair of equipment in the Administration Building ITS Cold Room. (Fiscal Impact: $60,000 Expense; Property Management Fund; Not Budgeted; Discretionary)
[4/5 vote required]

body

BACKGROUND

Public Works’ Property Management division requires a budget amendment to increase appropriation for Maintenance Building & Improvements by $60,000 to pay for a necessary repair of a cooling unit in the ITS network cold room, located in the basement of the Administration Building. The increase in appropriation will be offset by use of Appropriation for Contingency from the Property Management Fund. The repair needs to be completed in advance of summer weather to ensure proper temperatures are maintained in the equipment room. There are two cooling units, and both are at the end of their useful life, but full replacement is not feasible at this time because of the long lead time to obtain replacement units. Replacement of two coils within the unit that is currently malfunctioning will meet existing needs and it is anticipated that the repair will extend the life of the unit by several years. This is an essential unit, and the repair must be done as soon as possible. Replacement of both units will be programmed for the future. 

FISCAL & STRATEGIC PLAN IMPACT

Is there a Fiscal Impact?

Yes

Is it currently budgeted?

No

Is it Mandatory or Discretionary?

Discretionary

Discretionary Justification:

The increase in appropriation is necessary to cover the expense for repair of critical equipment within the building. The repair is necessary to protect the County network equipment.

Is the general fund affected?

No

Future fiscal impact:

There is no known future fiscal impact.

Consequences if not approved:

If not approved, alternative funding would be needed to pay for the repair of the cooling unit, which is necessary for the County network equipment.

ENVIRONMENTAL IMPACT

ENVIRONMENTAL DETERMINATION: The proposed action is not a project as defined by 14 California Code of Regulation 15378 (State CEQA Guidelines) and therefore CEQA is not applicable.