TO: Board of Supervisors
FROM: Steven Lederer - Director of Public Works
REPORT BY: Daniel Basore - Engineering Supervisor
SUBJECT: Amendment to Professional Services Agreement No. 220210B with YEI Engineers, Inc. in Support of 1127 First Street HVAC Replacement Project, PW 21-23

RECOMMENDATION
title
Director of Public Works requests the following:
1. Approval of and authorization for the Chair to sign Amendment No. 1 to Agreement No. 220210B with YEI Engineers, Inc. increasing maximum compensation by $109,981 for a new maximum of $300,544 for additional engineering design and support services for the 1127 First Street HVAC Replacement Project, PW 21-23; and
2. Approval of a Budget Transfer for the following (4/5 votes required):
a. Increase appropriations by $109,981 in the Accumulated Capital Outlay Fund (ACO) (Fund 3000, Org 3000000) with the use of its available fund balance to be transferred to Project 21070; and
b. Increase appropriations by $109,981 in 1127 First Street HVAC Replacement Project budget (Fund 3000, Org 3000550, Project 21070) offset by a transfer-in revenue from the ACO.
body
EXECUTIVE SUMMARY
On December 14, 2021, the Board of Supervisors (Board) approved a professional service agreement with YEI Engineers, Inc. to develop a design for replacing the heating, ventilation, and air conditioning (HVAC) units on 1127 First Street building. In addition to evaluation of the HVAC units, YEI also observed issues with the existing roofing of the building jeopardizing the feasibility of implanting the HVAC project. Public Works staff utilized an on-call architectural firm to evaluate the roof which confirmed the observed issues raised by YEI. The proposed amendment expands YEI’s contract to design a roofing system compatible with the HVAC project and verifies that the existing buildings roof’s structural capacity is sufficient for the two improvements.
PROCEDURAL REQUIREMENTS:
1. Staff reports.
2. Public comments.
3. Motion, second, discussion and vote on the item.
FISCAL & STRATEGIC PLAN IMPACT
|
Is there a Fiscal Impact? |
Yes |
|
Is it currently budgeted? |
Yes |
|
Where is it budgeted? |
The project is budgeted in Capital Improvement Project Fund 3000, Org 3000550, Project 21070 |
|
Is it Mandatory or Discretionary? |
Discretionary |
|
Discretionary Justification: |
Approval of this amendment is needed to compensate YEI Engineers Inc. to provide additional design and construction support services for the new HVAC design for the project. |
|
Is the general fund affected? |
Yes |
|
Future fiscal impact: |
The construction will begin in 2023. Maintenance of the new units will have an ongoing fiscal impact. |
|
Consequences if not approved: |
The existing rooftop will not be able to support the weight of the new HVAC units and does not meet the building code. |
|
County Strategic Plan pillar addressed: |
Healthy, Safe, and Welcoming Place to Live, Work, and Visit |
|
Additional Information |
None |
ENVIRONMENTAL IMPACT
ENVIRONMENTAL DETERMINATION: The proposed action is not a project as defined by 14 California Code of Regulations 15378 (State CEQA Guidelines) and therefore CEQA is not applicable.
BACKGROUND AND DISCUSSION
Public Works staff conducted a qualifications based process for the selection of a firm to provide design and engineering along with construction support, inspections, and associated services for the study and replacement of the HVAC units for the 1127 First Street County facility. From the Request for Qualifications, YEI Engineers Inc. was determined to be the most qualified firm to provide these services and on December 14, 2021, the Board of Supervisors approved a professional services agreement (PSA) with YEI for a not to exceed agreement of $190,563.
YEI completed their study and submitted a technical memorandum with the recommendation of increasing the tonnages of the HVAC units in order to meet the cooling demands of the 1127 First Street facility during summer. However, along with the added weight of the increased size of the units, YEI recommended that an evaluation of the roofing system be conducted based on site observation and discussions with a roofing contractor suspecting that the existing roof contains more than two roofing layers, which makes the replacement of the HVAC units infeasible as the structural roof would not have capacity to support both the HVAC units and the existing multiple roofing layers. Therefore, the County conducted an evaluation of the existing roofing system using their on-call architectural firm. The roof evaluation confirmed that there are more than two layers of roofing material on the majority of the roof which exceeds the current building code requirements of a maximum of two layers of roof material, along with other deficiencies that contribute to leaks and drainage issues on the existing roof.
Consequently, based on the YEI’s HVAC study, their roof observation, and a roof evaluation, Public Works staff is requesting an amendment to YEI’s agreement to include a roofing design, to be compatible with the proposed HVAC replacements, and conducting a structural analysis of the existing roof at 1127 First Street ensuring the two improvements are within its existing structural capacity and eliminating the leaks and drainage issues.
The Director of Public Works recommends the approval Amendment Number 1 to the PSA and a budget transfer for an additional $109,981 to compensate YEI for additional design and construction support services for the HVAC replacement project.
SUPPORTING DOCUMENT
1. Amendment Number 1 to Agreement No. 220210B