File #: 25-1540    Version: 1
Type: Report Status: Agenda Ready
File created: 8/20/2025 In control: Board of Supervisors
On agenda: 9/9/2025 Final action:
Title: Award a Construction Contract to Granite Rock Company for the "Rossi Bridge Phase 1," RDS 25-25 project (Fiscal Impact: $956,275 Expense; Capital Improvement Projects Fund; Budgeted; Discretionary)
Sponsors: Board of Supervisors
Attachments: 1. Budget Summary - Phase 1, 2. Budget Summary - Phase 1 and 2
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

 

TO:                     Board of Supervisors

FROM:                     Steven Lederer, Director of Public Works

REPORT BY:                     Frank Lucido, Engineering Manager

SUBJECT:                     Construction Contract Award for the “Rossi Bridge Phase 1”, RDS 25-25 project.

 

RECOMMENDATION

title

Award a Construction Contract to Granite Rock Company for the “Rossi Bridge Phase 1,” RDS 25-25 project (Fiscal Impact: $956,275 Expense; Capital Improvement Projects Fund; Budgeted; Discretionary)

body

 

BACKGROUND

The crossing on Rossi Road that bridges over Conn Creek is unique in that it was originally constructed by private owners in the early 1900’s by placing three iron culverts in the creek and placing soil on top which partially impounded the creek. In the late 1920’s the County assumed responsibility for the road and constructed an additional concrete box culvert and headwall to allow for more capacity. In early February of 2025, a storm event caused significant damage around Napa County including the Rossi Crossing. One of the iron culverts collapsed and the concrete headwall was severely damaged.
The County Board ratified a local emergency proclamation on February 18, 2025, and approved $2,000,000 in funding for the Rossi Road Bridge Repair Project. On March 11, 2025, the Board approved a $348,447 contract with Adko Inc., who was previously selected in a request for qualifications process for storm repair projects to continue design work and environmental review. The final design and environmental documents were submitted to local, state and federal agencies, however permission to work in the creek has not been granted yet. This phase of the project will focus on constructing improvements outside of the creek prior to this coming winter which will make it possible to launch a bridge more quickly if the existing impound fails. During construction the crossing, which is the only public access to a business and 7 or 8 residences will be closed during the weekdays for several weeks. The County entered into an agreement with a private property owner to allow for limited local traffic access through their property during these closure times.
The County expects permits for Phase 2 of the project by next summer which will allow for the removal of the earthen impound, re-grading the creek and installation of the new bridge. Both phases will require archaeological, cultural and biological monitors and special environmental surveys.

On July 22, 2025 the Board approved advertising this project and August 21, 2025 bids were opened with the results listed below:

Granite Rock Construction Company     Santa Jose, CA           $431,020
Vaca Valley Excavating & Trucking      Vacaville, CA            $568,882
Valentine Corporation                             San Rafael, CA          $578,369
E.E. Gilbert Construction, Inc.                Martinez, CA             $646,267
Granite Construction Company               Ukiah, CA                 $745,770

The engineer's construction estimate was $600,000. Staff recommends award to Granite Rock Company for their responsive total bid of $431,020. Construction is anticipated to commence in September of 2025 and be completed by December of 2025, weather and site conditions permitting. A 25% contingency is budgeted for any unforeseen items because of the significant potential for unforeseen during drilling.
Granite Rock Company is not a local vendor; however, the Public Contract Code requires that the construction contract be awarded to the lowest responsible and responsive bidder regardless of whether the low bidder is local or not. Staff reached out to the local construction contractor community by advertising the request for bids in the Napa Valley Register and the Solano-Napa Builder's Exchange, and by posting on the County website.  Staff also sent "Notices to Contractors" to the local construction community.

Requested Action:
Award a construction contract for the “Rossi Bridge Phase 1, RDS 25-25” project to Granite Rock Company for their low total bid of $431,020.

 

FISCAL IMPACT

Is there a Fiscal Impact?

Yes

Is it currently budgeted?

Yes

Where is it budgeted?

Roads CIP Project 25034

Is it Mandatory or Discretionary?

Discretionary

Discretionary Justification:

This action is needed to ensure public and emergency access.

Is the general fund affected?

No

Future fiscal impact:

This is the first phase of the project will be completed in FY 24-25 while the second phase will be completed in FY 25-26. The site will also require funding for mitigation planting and reporting for 5-10 more years after the completion of the second phase.

Consequences if not approved:

If this project isn’t approved and the region receives moderate rain this winter, there is a good chance that the road will fail and there won’t be a method to restore access until the end of next summer.

Additional Information

The County has drafted a temporary access agreement with Rodgers Vineyard which will allow limited use by the residents who live beyond the damaged section of the road. As part of the agreement, the County will repair damage to the private road in exchange for its use during construction and in case of an emergency. The estimated cost for this access/maintenance through the life of the project is roughly $50,000.

 

ENVIRONMENTAL IMPACT

ENVIRONMENTAL DETERMINATION: The proposed improvements would be considered Categorically Exempt from CEQA pursuant to Section 15301 Class 1-Existing Facilities, which includes the operation and repair of existing public or private structures or facilities involving negligible or no expansion of existing of former use. The proposed improvements would also be considered Categorically Exempt pursuant to Section 15302, Class 2- Replacement or Reconstruction, which consists of replacement or reconstruction of existing structures and facilities where the new structure will be located on the same site as the structure replaced and will have substantially the same purpose and capacity as the structure replaced. A key consideration in the appropriateness of using these Categorical Exemptions is whether the project would be located on the same site, have substantially the same purpose and involves negligible or no expansion of an existing use. In terms of negligible expansion, the proposed project will generally take place within the existing facility’s footprint and does not include significant expansions beyond existing conditions. The proposed project would allow repair work and improve public safety and ensure the bridge remains safe for use by the Napa County residents and visitors to the area. Therefore, it has been determined that the proposed project qualifies for both a Class 1 and Class 2 Categorical Exemption and has no reasonable possibility of having a significant effect on the environment.