Skip to main content
Napa County Logo
File #: 24-761    Version: 1
Type: Report Status: Agenda Ready
File created: 4/24/2024 In control: Board of Supervisors
On agenda: 5/7/2024 Final action: 12/31/2023
Title: Approve a Budget Amendment to appropriate funding from SB-1 Non-Operating Special Revenue Fund for the "Zinfandel Bridge Approach Scour Project." (Fiscal Impact: $100,000 Expense; SB-1 Non-Operating Special Revenue Fund; Not budgeted; Discretionary) [4/5 Vote Required]
Sponsors: Board of Supervisors
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

 

TO:                     Board of Supervisors

FROM:                     Steve Lederer - Director of Public Works

REPORT BY:                     Frank Lucido, Engineering Manager

SUBJECT:                     Approval of a Budget Transfer for the “Zinfandel Bridge Approach Scour Project”, RDS 24-23

RECOMMENDATION

title

Approve a Budget Amendment to appropriate funding from SB-1 Non-Operating Special Revenue Fund for the “Zinfandel Bridge Approach Scour Project.” (Fiscal Impact: $100,000 Expense; SB-1 Non-Operating Special Revenue Fund; Not budgeted; Discretionary)
[4/5 Vote Required]

body

BACKGROUND

Zinfandel Bridge over the Napa River has been serving the County since 1913. Since its original construction, the valley has experienced several major floods and changes to the channel. At some point a concrete wall was constructed adjacent to the southwest corner of the bridge to provide additional support to the roadway and in 2013 a major project was completed underneath the bridge to promote fish passage. During a recent inspection of the bridge a large scour hole was discovered below the concrete wall that was constructed to support the roadway. To design a long lasting and effective repair, engineers need to know how deep the scour will go and what type of forces are expected in the area. Funding is being requested so that a two-dimension hydraulic model can be completed, and initial design started. After this step, staff will have a better understanding of project costs and will return to the Board of Supervisors with a report of findings and a request to fund final design and permitting. The permitting is expected to be rigorous and time consuming, however, staff will emphasize the importance of getting the project completed as soon as possible to the various agencies.

Requested Action:
1. Approve a Budget Amendment for the following (4/5 vote required):
a. Increase Transfers Out appropriations by $100,000 in the SB-1 Non-Operating Special Revenue Fund (Fund 2440, Sub-Division 1220052, Account 56100) (SB-1 SRF) offset by use of its available fund balance to transfer to Project 24030; and
b. Increase Engineering Services appropriations by $100,000 in Project 24030 budget (Fund 2040, Sub-Division 2040500, Project 24030, Account 52145) offset by Transfer In revenue from SB-1 SRF.  

 

FISCAL & STRATEGIC PLAN IMPACT

Is there a Fiscal Impact?

Yes

Is it currently budgeted?

No

Is it Mandatory or Discretionary?

Discretionary

Discretionary Justification:

Budget is needed to start design.

Is the general fund affected?

No

Future fiscal impact:

Funding will be needed in FY 24-25 for final design, permitting and construction. Permits may require mitigation planting and monitoring for up to 10 years after construction completion.

Consequences if not approved:

At least a portion of Zinfandel could be lost which would be a major disruption to traffic flow in the area.

 

ENVIRONMENTAL IMPACT

ENVIRONMENTAL DETERMINATION: The proposed action is not a project as defined by 14 California Code of Regulations 15378 (State CEQA Guidelines) and therefore CEQA is not applicable.