TO: Board of Supervisors
FROM: Steven Lederer - Director of Public Works
REPORT BY: Frank Lucido - Engineering Manager
SUBJECT: “Hall of Justice Improvements for Long Term Court Holding”, PW 22-30, Budget Transfer

RECOMMENDATION
title
Director of Public Works requests approval of a Budget Transfer for the following regarding the “Hall of Justice Improvements for Long Term Court Holding”, PW 22-30 (4/5 vote required):
1. Increase appropriations by $100,000 in the Accumulated Capital Outlay (ACO), (Fund 3000, Org 3000000) offset by use of its available fund balance to transfer to Project 23013; and
2. Creation of a new project, “Hall of Justice Improvements for Long Term Court Holding” (Fund 3000, Org 3000505, Project 23013), and increase appropriations by $100,000 in Project 23013 budget offset by a transfer-in revenue from the ACO.
body
EXECUTIVE SUMMARY
The County is starting the process of evaluating the most efficient method for transporting inmates from the replacement jail site to downtown court holding in the existing jail and sufficient support spaces for staff assigned to work in the area in anticipation of the construction of the replacement jail. This high-level evaluation will take into account improvements that could be made to the existing facility, staffing resources, site conditions, legal requirements and costs.
FISCAL & STRATEGIC PLAN IMPACT
|
Is there a Fiscal Impact? |
Yes |
|
Is it currently budgeted? |
No |
|
Where is it budgeted? |
Project will be funded by the ACO. |
|
Is it Mandatory or Discretionary? |
Discretionary |
|
Discretionary Justification: |
This work is needed to start the process of determining the safest and most cost-effective method for court holding in the existing Hall of Justice once the replacement Jail is constructed. |
|
Is the general fund affected? |
Yes |
|
Future fiscal impact: |
It is anticipated that there will be a future fiscal impact to support studying preferred alternatives in further detail (most likely this fiscal year) and there may also be a need for funds to complete design and a construction project over the next few years. |
|
Consequences if not approved: |
If no improvements are completed, the existing facility could continue to be used; however, at a high cost because additional staff will be needed to operate the existing facility. |
|
County Strategic Plan pillar addressed: |
Effective and Open Government |
|
Additional Information |
None |
ENVIRONMENTAL IMPACT
ENVIRONMENTAL DETERMINATION: The proposed action is not a project as defined by 14 California Code of Regulations 15378 (State CEQA Guidelines) and therefore CEQA is not applicable. If a project is proposed at some point, staff will perform CEQA as required.
BACKGROUND AND DISCUSSION
The County is starting the process of evaluating the most efficient method for transporting inmates from the planned replacement jail site to the current court location and how to operate the facility during off hours. During the early planning stages of the Replacement Jail, it was anticipated that the current Ground Floor Housing Unit of the Jail (located in the basement) would be utilized as Court Holding. The Ground Floor Housing Unit provides an adequate number of holding cells to accommodate inmates awaiting court appearances and provides a direct connection to the basement tunnel which connects to the courthouse. However, identifying the secure pathway to gain entry to the Ground Floor Housing Unit, and how much staff will be needed for the operation, requires further exploration. Although some work was completed on this part of the project during the early days of planning for a new jail, more detailed work needs to be completed to account for changes in the existing jail facility over recent years and to find the best alternative for the County.
It is anticipated that continuing to use the existing facility will add cost to the project. Operating the Ground Floor Unit without completing any improvements will potentially have the highest annual operational cost but require the least amount of upfront investment. However, it is likely that investing in the completion of some level of improvements will eventually save the County money to operate this portion of the project. This high-level evaluation will assist the County in considering costs for various improvements and the associated staffing resources that are needed.
The $100,000 budget transfer being requested will give staff the ability to issue a task order to Nacht & Lewis Architects who was selected through a request for qualifications process to be on-call for various projects. In addition to the $62,980 task order, staff is requesting some funding for contingency and staff time.
After completion of the report, staff will return to the Board with an update and suggested next steps.
SUPPORTING DOCUMENTS
Project Budget