Title: Staff is requesting approval and authorization for the Chair to sign the third Amendment for Agreement 2024-03 with R3 Consulting Group, Inc. for an additional $20,000, with an adjusted total contract amount not to exceed $180,000. This increase will be to conduct a non-disposal rate study at our Devlin Road Transfer Station (DRTS).
Attachments: 1. R3 Consulting - Amendment #3
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

 

TO:                     Napa-Vallejo Waste Management Authority Board of Directors

FROM:                     Chris Celsi, Executive Director

REPORT BY:                     Chris Celsi, Executive Director

SUBJECT:                     Third Amendment - R3 Consulting Group

RECOMMENDATION

title

Staff is requesting approval and authorization for the Chair to sign the third Amendment for Agreement 2024-03 with R3 Consulting Group, Inc. for an additional $20,000, with an adjusted total contract amount not to exceed $180,000. This increase will be to conduct a non-disposal rate study at our Devlin Road Transfer Station (DRTS).

body

EXECUTIVE SUMMARY

Napa-Vallejo Waste Management Authority (NVWMA) is requesting approval of a contract extension R3 Consulting Group, Inc. Previously, NVWMA staff hired R3 Consulting Group to aid the Authority in reviewing scope of services, contract negotiations with Northern Recycling Operations and Waste Services (NROWS) and conduct a rates and services survey to determine appropriate gate fees at Devlin Road Transfer Station. Specifically, to determine the appropriate rate to charge for MSW, clean concrete, clean dirt and private vehicle customers. R3 Consulting Group is very familiar with solid waste practices in the NVWMA service area.

The request is to increase appropriations in FY 2026-27 by $20,000 to cover costs to study and determine proper tipping fees for special items, such as tires, mattresses, appliances, boats and other “non-disposal” material at the Devlin Road Transfer Station.

FISCAL & STRATEGIC PLAN IMPACT

Is there a Fiscal Impact?

Yes

Is it currently budgeted?

Yes

Where is it budgeted?

Operating Expenses - Devlin Road Transfer Station

Is it Mandatory or Discretionary?

Discretionary

Discretionary Justification:

R3 Consulting Group has the expertise staff needed to provide NVWMA recommendations to charge appropriate DRTS gate rates.

Consequences if not approved:

NVWMA may not provide appropriate customer gate rates for other items at DRTS.

ENVIRONMENTAL IMPACT

ENVIRONMENTAL DETERMINATION: The proposed action is not a project as defined by 14 California Code of Regulations 15378 (State CEQA Guidelines) and therefore CEQA is not applicable.