TO: Board of Supervisors
FROM: Steven Lederer, Public Works Director
REPORT BY: Steven Lederer, Public Works Director
SUBJECT: Receive a report on emergency projects currently under construction

RECOMMENDATION
title
Approve a report of emergency Public Works actions on two projects as authorized by Resolution No. 2015-37, determine that the emergency does not permit the delay associated with competitive bidding procedures, and that the emergency actions are necessary to respond to the emergency pursuant to Public Contract Code Section 22050(c)(1) and affirm the need to continue this action. (No Fiscal Impact)
[4/5 vote required]
body
BACKGROUND
Project 1: Pope Canyon Rd. Mile Post Marker (MPM) 4.35
Recent storms caused significant damage to the County road system, resulting in the Board of Supervisors declaring a state of emergency. Some of the sites required immediate action to protect the public and ensure the damage does not spread to other areas. The County used emergency contracting procedures to initiate work on these areas, which allowed for reduced time to hire contractors to perform the work.
Project 2: Yountville Fire Department Bathroom Emergency Repairs
Severe leaks and water damage, which is potentially jeopardizing the normal use of the station, have been identified at the Napa County Fire Department Station 12, located at 7401 Solano Ave, Yountville, CA 94599. Public Works and the Fire Department Chiefs met to discuss the safety concerns of occupying a building with potential biological growth. In addition, the urinal became inoperable due to leaks and the building bathroom was insufficient to serve the staff at the fire station. The conditions of the building made the long design period and competitive bidding process, which would not start until October 2025, to be insufficient to keep the fire station operational. Without repairing the bathroom as an emergency, Fire could need to relocate staff to a temporary housing option, which would induce higher cost and a decrease in public safety due to the longer response time to travel back to the station.
Per Public Contract Code section 22050(c)(1), when the Board orders expedited contracting procedures be used, the Board shall review the emergency action at its next regularly scheduled meeting and at every regularly scheduled meeting thereafter (but not more often than every 14 days) until the action is terminated, to determine, by a four-fifths vote, that there is a need to continue the action.
The status of each project, and the estimated cost of each project, currently underway using this contracting provision is provided below:
Pope Canyon Rd. 4.35 ($550,000): Mobilization and setting of traffic control commenced 7/21. Construction is planned for 7/28 to 8/22 (dependent on drilling conditions).
Yountville Fire Station Bathroom Emergency Repairs ($373,620): Materials have been ordered. Construction is planned for 8/5-8/24.
The Board has previously approved funding and no additional funds are being requested at this time. Good progress is being made, and staff recommends continuing these projects to conclusion in order to expeditiously protect public safety and property.
Requested Action:
Approve the above report and affirm that these projects should continue under the expedited contracts.
[4/5 vote required]
FISCAL IMPACT
Is there a Fiscal Impact? |
No |
Is it Mandatory or Discretionary? |
Discretionary |
Discretionary Justification: |
Approval of this action will allow these important safety projects to proceed to completion in an expeditious manner. |
Consequences if not approved: |
If not approved, the projects underway will be stopped until formal bidding procedures can be conducted, resulting in month’s delays in restoring this important infrastructure. |
ENVIRONMENTAL IMPACT
ENVIRONMENTAL DETERMINATION: General Rule. It can be seen with certainty that there is no possibility the proposed action may have a significant effect on the environment and therefore CEQA is not applicable. [See Guidelines For the Implementation of the California Environmental Quality Act, 14 CCR 15061(b)(3)].