TO: Board of Supervisors
FROM: Steven Lederer, Director of Public Works
REPORT BY: Dewey Phan, Assistant Engineer
SUBJECT: Construction Contract Award for the “Redwood Road MPM 5.41 Project,” RDS 26-22

RECOMMENDATION
title
Award a Construction Contract to North Bay Excavation, Inc., of Valley Ford, CA in the amount of $158,325 for the “Redwood Road MPM 5.41 Project,” RDS 26-22. (Fiscal Impact: $234,906 Expense for the construction contract and other project costs; General Fund, Reallocation of Budget; Discretionary)
body
BACKGROUND
The November 2025 storms caused a small landslide that undermined about 33 linear feet of the roadway edge, leaving part of the asphalt concrete road unsupported and creating a steep drop down to a private driveway. To ensure the future stability of the road and provide public safety, staff propose to repair the damage by installing a new rock slope protection (RSP) buttress to stabilize the downhill shoulder of 4620 Redwood Road at a 1:1 slope, about ten feet high, averaging five feet in thickness. Following installation of the RSP, about 100 feet of the damaged road surface will be reconstructed or repaved.
The Board authorized advertising for the project on June 16, 2026, and the Public Works staff opened bids on July 21, 2026, with the results listed below:
North Bay Excavation, Inc. Valley Ford, CA $158,325
Maggiora & Ghilotti San Rafael, CA $195,195
Rege Construction Cloverdale, CA $218,239
Rehak Construction LLC Auberry, CA $223,731
Peters Excavating, Inc. Sebastopol, CA $229,974
Gaub Trucking Corp San Ramon, CA $234,082
W.R. Forde Associates, Inc. Richmond, CA $244,515
Imperial Construction & Engineering, Inc. Roseville, CA $247,451
Gravity Construction Lodi, CA $251,959
Cats4U, Inc. Healdsburg, CA $252,440
Roots Strong Builder American Canyon, CA $259,168
Norgo Engineering American Canyon, CA $266,520
Broderick General Engineering Sonoma, CA $273,265
Ground Control, Inc. San Francisco, CA $281,088
Taylor-Bailey, Inc St. Helena, CA $283,556
Staff recommends award to North Bay Excavation, Inc. for their responsive total bid of $158,325. Construction is anticipated to commence in September 2026 and to be completed by November of 2026, weather and site conditions permitting. A 25% construction contingency of $39,581 is requested for any unforeseen items of work. $124,870 for Design and Engineering Consultant, $12,338 for Survey and Topographic Map, $60,000 for Construction Management, $80,000 for County Project management and administration, $59,386 for Environmental, Geotechnical and Special Inspections and $5,000 for any Mailers, Newspaper Advertisements and Permits. The total project budget is $539,500 of which $304,594 was already approved by the board on March 10, 2026.
Included in the Fiscal Year 2026-27 budget is $7 million in Project RDS01 for a list of 2025 November Storm projects with not-to-exceed project amounts approved by the Board. Redwood Road MPM 5.41 also known as Redwood Rd MPM 5.41 Slide Repair (26023) was on the list with a not-to-exceed amount of $1,000,000. With respect to this agenda item, a budget amendment and subsequent transfer of funds will be prepared to reallocate $234,906 from RDS01 to Project 26023. These actions will be reviewed and approved by the County Executive Office and the Auditor-Controller Office to ensure compliance with the adopted budget and availability of funds.
North Bay Excavation, Inc. is not a local vendor; however, the Public Contract Code requires that the construction contract be awarded to the lowest responsible and responsive bidder regardless of whether the low bidder is local or not. Staff reached out to the local construction contractor community by advertising the request for bids in the Napa Valley Register, Solano-Napa Builder's Exchange, OpenGov and by posting on the County website. Staff also sent "Notices to Contractors" to the local construction community.
Requested Actions:
1. Award of a construction contract for the “Redwood Road MPM 5.41 Project, RDS 26-22” to North Bay Excavation, Inc., of Valley Ford, CA for their low total bid of $158,325 and authorization for the Chair to sign the construction contract.
FISCAL IMPACT
|
Is there a Fiscal Impact? |
Yes |
|
Is it currently budgeted? |
Yes |
|
Where is it budgeted? |
Roads Fund, Division 20405 |
|
Is it Mandatory or Discretionary? |
Discretionary |
|
Discretionary Justification: |
Repairs are necessary to prevent further damage and ensure public safety. |
|
Is the general fund affected? |
Yes |
|
Future fiscal impact: |
Funding will be needed in fiscal year 2026-27 for construction. |
|
Consequences if not approved: |
Slide could damage more of the roadway which could potentially remove road access for residents and result in a major disruption of emergency response in the affected areas. |
|
Strategic Initiative |
Build healthy, connected communities |
ENVIRONMENTAL IMPACT
ENVIRONMENTAL DETERMINATION: Consideration and possible adoption of a Categorical Exemption Class 1: It has been determined that this type of project does not have a significant effect on the environment and is exempt from the California Environmental Quality Act. See Class 1 (“Existing Facilities”) which may be found in the guidelines for the implementation of the California Environmental Quality Act at 14 CCR §15301; see also Napa County’s Local Procedures for Implementing the California Environmental Quality Act, Appendix B.]