TO: Members of the Governing Board
FROM: Christopher Silke - District Engineer
REPORT BY: Christopher Silke - District Engineer
SUBJECT: Approval of Plans and Specifications and Authorization to Advertise for Bids for Lift Station A - Sewer Collection Tank Replacement Project, LB 22-03.

RECOMMENDATION
title
Approve plans and specifications for the Lift Station A - Sewer Collection Tank Replacement Project, LB 22-03 and authorization to advertise for sealed bids and opening of the bids at a time, date, and location to be published by the District Engineer pursuant to Section 20150.8 of the Public Contract Code. (No Fiscal Impact, Discretionary)
body
BACKGROUND
The President authorized the American Rescue Plan Act (ARPA) in March 2021 to allocate $1.9 trillion in stimulus monies across a variety of programs. Of the total, $350 billion is allocated to state, local, territorial and Tribal governments to enable them to continue to support the public health response and to lay the foundation for a strong and equitable economic recovery. The U.S. Department of the Treasury released Final Interim Rule regulations on May 10, 2021 defining eligible use of ARPA monies that includes investments into water and sewer utility infrastructure. Local Fiscal Recovery (LFR) funds must be obligated by December 31, 2024 with projects completed no later than December 31, 2026. Napa County received $26,755,157 for ARPA appropriations.
Based on the Final Rule guidelines, water and sewer utility projects that would qualify for funding under the Safe Drinking Water and Clean Water Act Programs are deemed as eligible under ARPA. The District has four (4) high priority projects that satisfy ARPA and the Drinking and Clean Water Act funding criteria - one of the projects being the subject of this agenda report - the replacement of the 91,000 gallons raw sewage collection tank located at Sewer Lift Station A.
History of the Collection Tank at Lift Station A:
The original sewer collection tank at Lift Station A, which collects all raw sewage from Unit 2 of the Berryessa Estates subdivision, was installed in 1967. The tank was constructed of welded steel with a maximum capacity of approximately 50,000 gallons. In the late 1980s/early 1990s, deterioration of the upper tank wall due to corrosion from hydrogen sulfide vapors caused seepage of raw sewage from the upper tank panels requiring the operational level to be lowered to half the height of the tank. Due to lack of funding for full replacement of the tank, a reduced scope project was approved that required removal of the corroded panels above the reduced operational level - leaving the District with limited sewer collection capacity for growth and or storm events.
The tank was operated at this reduced capacity for over a decade; increased flow as a result of community growth, and also from increased inflow and infiltration (I/I) in the collection system, resulted in multiple overflows from the tank and violations from the Central Valley Regional Water Quality Control Board (CVRWQCB). An Administrative Civil Liability Complaint (ACL) that required payment of a fine, was issued and ultimately rescinded, but the District was required to replace the tank with a capacity sufficient to prevent overflows in the future.
In 2002, District engineering staff solicited bids for replacement of the modified original welded steel tank with a 91,000 gallon bolted steel tank. The solicitation required setting the new tank within the footprint of the original tank, and the reuse of the original pad. The vendor, International Tank, Dry & Liquid Storage, Inc. from Kentucky was retained to complete the project design and installation.
The 91,000 gallon tank is now 20 years old, and as with the original tank installation, corrosion and pitting, due to the accumulation of hydrogen sulfide gases, has accelerated along the top tank panels that sit above the operational liquid level of the tank. In an effort to prevent a repeat of prior violations and potential ACLs from the CVRB due to illicit discharges from the tank, staff proposed immediate replacement of the tank pending award of funding availability through the ARPA program.
On February 8, 2022, the District and Napa County executed a Memorandum of Understanding (MOU) outlining the terms of the transfer of the $800,000 ARPA earmark for the project, and on June 21, 2022, staff publicly advertised an RFQ / RFP engineering services package detailing the scope of work, submittal instructions and deadline for the Sewer Lift Station A Tank Replacement Project. After evaluation of the two proposals received, staff recommended and the Board awarded a contract to GHD, Inc. in the amount of $190,674 on September 13, 2022.
Design plans and specifications to demolish the corroded steel tank and construct a new cast-in-place reinforced concrete were approved and authorized to solicit competitive public bids by the Governing Board at its May 16, 2023 meeting. Contractor bids were subsequently opened on July 13, 2023. The lowest qualified bid exceeded ARPA appropriations to award a Contract. All Contractor bids were rejected by the Governing Board in the August 8, 2023 meeting. Supplemental project appropriations in the amount of $1,400,000 from Napa County for water and wastewater improvements were then secured as part of a larger funding award from the Department of Water Resources through the California Budget Act of 2022 (AB 179, Stats. 2022, ch. 249, § 207). Including the remaining ARPA funding available, project appropriations with the DWR award totaled $2,009,326.
District staff and GHD, Inc. design team deliberated the feasibility of downsizing concrete tank capacity and geometry simultaneous with replacing the remaining segment of undersized sewer force main as an alternative approach to upgrade sewer collection infrastructure. Preliminary engineer estimates to construct a smaller concrete tank and increase the sewer force main diameter that will enhance Lift Station A pumping capacity totaled less than the ARPA / DWR project appropriations budgeted for construction. On December 19, 2023 Amendment No 1 to the GHD, Inc. Agreement was approved by the Governing Board, authorizing the change to the scope of the project design and directing GHD, Inc. to produce revised plans and specifications. Engineering design budget was increased by $49,114 for an adjusted total of $239,788, leaving total appropriations of ARPA/DWR funding of $1,960,212 to fund construction related services.
Construction plans and specifications are now complete and include replacement of the existing steel tank with a new cast-in-place reinforced concrete tank of 50,000 gallons capacity paired with replacement of the original 1960’s asbestos cement pipe sewer force main that will improve pumping efficiency. The new tank will be installed in the same location as the existing tank. Additional project components include a new tank foundation, piping reconfiguration to allow better control of waste volumes entering the tank, and other miscellaneous site improvements necessary to install the tank in the same footprint as the existing tank. The engineer’s opinion of probable construction cost is approximately $1,750,000.
With the revised scope design plans and specifications now complete, the District Engineer requests approval to advertise the project for sealed bids and opening of the bids at a time, date, and location to be published by the District Engineer pursuant to Section 20150.8 of the Public Contract Code.
FISCAL & STRATEGIC PLAN IMPACT
Is it Mandatory or Discretionary? |
Discretionary |
Discretionary Justification: |
Approval of plans and specifications and authorization to advertise for sealed bids is necessary prior to the construction phase. |
Is the general fund affected? |
No |
Consequences if not approved: |
If not approved the Project will not go out for construction bids and the likelihood of a tank failure due to corrosion will increase with time, putting the District at risk of violating the Waste Discharge Requirements (permit) issued by the Central Valley Regional Board. |
ENVIRONMENTAL IMPACT
Consideration and possible adoption of a Categorical Exemption Class 1: It has been determined that this type of project does not have a significant effect on the environment and is exempt from the California Environmental Quality Act. [See Class 1 (“Existing Facilities”) which may be found in the guidelines for the implementation of the California Environmental Quality Act at 14 CCR §15301; see also Napa County’s Local Procedures for Implementing the California Environmental Quality Act, Appendix B.]