TO: Board of Supervisors
FROM: Steven Lederer, Director of Public Works
REPORT BY: Sydney Barclay, Associate Engineer
SUBJECT: Approval of Plans and Specifications and Authorization to Advertise for Bids for the “Chiles Pope Valley Road MPM 3.63 Culvert Repair Project”, RDS 22-27

RECOMMENDATION
title
Approve the Plans and Specifications for the “Chiles Pope Valley Road MPM 3.63 Culvert Repair Project” and authorize to advertise for sealed bids, and opening of the bids at a time, date, and location to be published by the Director of Public Works pursuant to Section 20150.8 of the Public Contract Code. (No Fiscal Impact; Discretionary)
body
BACKGROUND
The Chiles Pope Valley Rd MPM 3.63 project started off as a guardrail replacement project, however, after further inspection, the existing bank located below the guardrails was eroded and the culvert is incapable of handling the flows of lower Chiles Creek. The Chiles Pope Valley Road MPM 3.63 project required hydraulic, geotechnical, archaeological, and biological studies to determine the most suitable repair to the culvert at this location. As a result of these studies, the County will be removing existing concrete wingwalls at the project site, constructing new concrete wingwalls on each side of the culvert (upstream and downstream), pouring a concrete slab approach at the inlet of the culvert, providing rock slope protection at the outlet of the culvert, and providing safety improvements on the roadway, which include new guardrails and concrete bridge barriers.
Moreover, because these repairs will occur within the channel and banks of lower Chiles Creek, the United States Army Corps of Engineers, the California Department of Fish and Wildlife, and the San Francisco Regional Water Quality Control Board required the County to obtain permits. These agencies have implemented strenuous requirements on the Chiles Pope Valley Road MPM 3.63 Project and require Tribal Monitoring, Biological Studies and Monitoring, and the implementation of a five (5) year Restoration Planting Plan.
The Engineer’s Estimate for the Chiles Pope Valley Rd MPM 3.63 Culvert Repair project is $675,000. The Plans and Specifications are complete and ready for approval by the Board of Supervisors. The Director is requesting authorization to advertise for bids. Staff will return to the Board of Supervisors at the time of construction to present a detailed project budget based on the lowest responsible bid and to request a budget amendment to fund construction.
Requested Actions:
1. Approve Plans and Specifications for the “Chiles Pope Valley Rd MPM 3.63 Culvert Repair Project”, RDS 22-27, and authorize to advertise for sealed bids.
FISCAL & STRATEGIC PLAN IMPACT
|
Is there a Fiscal Impact? |
No |
|
Is it currently budgeted? |
No |
|
Is it Mandatory or Discretionary? |
Discretionary |
|
Discretionary Justification: |
This project is improving the safety of road users and will ensure the existing bridge and culvert crossing do not wash out Chiles Pope Valley Road MPM 3.63, which is an emergency route. |
|
Is the general fund affected? |
No |
|
Future fiscal impact: |
Construction will begin and be completed in FY 2025-26; however, the regulatory permits issued for the project require five (5) years of mitigation and monitoring, which is expected to be completed in FY 2030-31. |
|
Consequences if not approved: |
This project will not move forward to the construction phase. |
ENVIRONMENTAL IMPACT
ENVIRONMENTAL DETERMINATION: Adoption of a Categorical Exemption Class 1: It has been determined that this type of project does not have a significant effect on the environment and is exempt from the California Environmental Quality Act. [See Class 1 (“Existing Facilities”) which may be found in the guidelines for the implementation of the California Environmental Quality Act of 14 CCR §15301; see also Napa County’s Local Procedures for Implementing the California Environmental Quality Act, Appendix B].