Title: Director of Public Works requests approval of the following Budget Transfer regarding the "JJC Security System Upgrade Project", PW 23-12 (4/5 vote required): 1. Increase appropriations by $30,000 in the Accumulated Capital Outlay (ACO) budget (Fund 3000, Org 3000000) offset by use of its available fund balance; and 2. Creation of a new Capital Improvement Project, "JJC Security System Upgrade Project" (Fund 3000, Org 3000504, Project 23021), and increase appropriations by $30,000 in Project 23021 budget offset by a transfer-in revenue from the ACO budget.
Attachments: 1. Budget Summary, 2. 22-1957 Board Letter
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

 

TO:                     Board of Supervisors

FROM:                     Steven Lederer - Director of Public Works

REPORT BY:                     Frank Lucido - Engineering Manager

SUBJECT:                     “JJC Security System Upgrade Project”, PW 23-12, Budget Transfer

 

RECOMMENDATION

title

Director of Public Works requests approval of the following Budget Transfer regarding the “JJC Security System Upgrade Project”, PW 23-12 (4/5 vote required):

1.                     Increase appropriations by $30,000 in the Accumulated Capital Outlay (ACO) budget (Fund 3000, Org 3000000) offset by use of its available fund balance; and 

2.                     Creation of a new Capital Improvement Project, “JJC Security System Upgrade Project” (Fund 3000, Org 3000504, Project 23021), and increase appropriations by $30,000 in Project 23021 budget offset by a transfer-in revenue from the ACO budget.

body

 

EXECUTIVE SUMMARY

The security system in the Juvenile Justice Center (JJC) was installed in 2005 when the building was constructed and some of the components that are needed to keep it functioning properly are no longer available. While the County is able to keep the system operating it will eventually need at least partial replacement. This item will create a project and provide funding for the investigation and production of a report to determine the best replacement strategy for the County. 

 

FISCAL & STRATEGIC PLAN IMPACT

Is there a Fiscal Impact?

Yes

Is it currently budgeted?

No

Where is it budgeted?

Project will be funded by the ACO.

Is it Mandatory or Discretionary?

Discretionary

Discretionary Justification:

This work is needed to determine the most cost effective method for retrofitting, repairing or replacing the security system at JJC.

Is the general fund affected?

Yes

Future fiscal impact:

It is anticipated that there will be a future fiscal impact to complete the design and construction phase for this project.

Consequences if not approved:

If no improvements are completed, the door control for at least part of the existing facility could eventually be impaired.

County Strategic Plan pillar addressed:

Effective and Open Government

Additional Information

None

 

ENVIRONMENTAL IMPACT

ENVIRONMENTAL DETERMINATION: The proposed action is not a project as defined by 14 California Code of Regulations 15378 (State CEQA Guidelines) and therefore CEQA is not applicable. If a project is proposed at some point, staff will perform CEQA as required.

 

BACKGROUND AND DISCUSSION

The security system in the Juvenile Justice Center is 17 years old and handles door control, audio and various alarms. Door opening is accomplished by manual push button switches that have a limited life and are becoming increasingly difficult to source. Although many spare parts for the system are on hand the supply is limited and the County will eventually need to find a solution that will keep the facility running efficiently into the future. The audio analog audio system, lighting controls and video system also need to be evaluated. 

 

The $30,000 budget transfer is being requested to move the project forward. After investigation is complete, staff will return to the Board with a recommendation on the best alternative. Investigation and design will be completed by Nacht & Lewis Architects who was selected through a request for qualifications process to be on-call for various projects.

 

 