Title: Approve the Plans and Specifications for the "2025 Annual Guardrail Repair, RDS 25-04" and authorization to advertise for sealed bids and opening of the bids at a time, date, and location to be published by the Director of Public Works pursuant to Section 20150.8 of the Public Contract Code. (No Fiscal Impact)
Sponsors: Board of Supervisors
Attachments: 1. Budget Summary
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TO: Board of Supervisors
FROM: Steven Lederer, Director of Public Works
REPORT BY: Dewey Phan, Assistant Engineer
SUBJECT: Approval of Plans and Specifications and Authorization to Advertise for Bids for the "2025 Annual Guardrail Repair, RDS 25-04"


RECOMMENDATION
title
Approve the Plans and Specifications for the "2025 Annual Guardrail Repair, RDS 25-04" and authorization to advertise for sealed bids and opening of the bids at a time, date, and location to be published by the Director of Public Works pursuant to Section 20150.8 of the Public Contract Code. (No Fiscal Impact)
body

BACKGROUND
The Public Works Department maintains 420 miles of roads and about 22 miles of guardrail. Over many years, the County has constructed guardrails to help prevent drivers from driving into the Napa River, into creeks, and down roadway embankments. Every year wayward drivers damage guardrails along County roads. In the past, County staff have hired contractors to repair individual damaged guardrails, or the Public Works Roads Division staff repaired the damage as time and funding allowed. With the advent of funding from SB-1, the County now designates about $500,000/year towards guardrail repairs.
The annual guardrail repair program provides safety for the public and is a more cost-effective method by repairing numerous guardrails with one construction contract to take advantage of economies of scale by. Staff prioritized the repairs based on safety and available funding and will repair the remaining damage (plus any newly damaged guardrails) in future years. On November 11, 2024, the Board of Supervisors approved $88,000 as a budget amendment for the engineering design of the project.
The Engineer's Construction Estimate for the 2025 Annual Guardrail Repair is $450,000. The Plans and Specifications are complete and ready for approval by the Board of Supervisors. The Director is requesting authorization to advertise for bids. Staff will return to the Board of Supervisors a...