Napa County Logo
File #: 23-0190    Version: 1
Type: Report Status: Agenda Ready
File created: 1/24/2023 In control: Board of Supervisors
On agenda: 2/7/2023 Final action:
Title: Director of Public Works requests adoption of a Mitigated Negative Declaration and Mitigation Monitoring and Reporting Plan for the Campbell Creek Culvert Project, which will allow staff to obtain necessary permits and take other actions needed to advance the project to construction.
Sponsors: Board of Supervisors
Attachments: 1. CDFW Comments, 2. Campbell Notice of Intent, 3. Campbell Creek Culvert Replacement (redline), 4. Campbell Creek Culvert MMRP
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TO: Board of Supervisors
FROM: Steven Lederer - Director of Public Works
REPORT BY: Frank Lucido, Engineering Manager
SUBJECT: Napa County Mitigated Negative Declaration for the Campbell Creek Culvert Project, RDS 22-01


RECOMMENDATION
title
Director of Public Works requests adoption of a Mitigated Negative Declaration and Mitigation Monitoring and Reporting Plan for the Campbell Creek Culvert Project, which will allow staff to obtain necessary permits and take other actions needed to advance the project to construction.

body
EXECUTIVE SUMMARY
The County is seeking to replace an undersized culvert on Campbell Creek that flows under Dry Creek Road and has prepared an Initial Study (IS) for the project pursuant to the California Environmental Quality Act (CEQA) and determined that a Mitigated Negative Declaration (MND) should be prepared. A Notice of Intent to Adopt a Mitigated Negative Declaration (MND) was circulated for public review and comment. Comments received from the California Department of Fish and Wildlife were addressed in the final IS/MND. According to the Mitigated Negative Declaration, the proposed project will have less than significant environmental impacts with the planned mitigation measures.

FISCAL & STRATEGIC PLAN IMPACT
Is there a Fiscal Impact?
Yes
Is it currently budgeted?
Yes
Where is it budgeted?
Fund 2040, Org 2040500 and Project 22012
Is it Mandatory or Discretionary?
Discretionary
Discretionary Justification:
The Board of Supervisors needs to adopt the IS/MND for the project to proceed to the construction phase.
Is the general fund affected?
No
Future fiscal impact:
Construction funding for the project is needed and expected to come in part from SB1 funds if outside grant funding is received or in whole if they are not.
Consequences if not approved:
The regulatory agencies will not issue permits, and the project will not move forward to construction.
County Strategic Plan pillar addressed:
Livable Economy for All