Title: District Engineer requests approval of and authorization for the Chair to sign Agreement No. 230149B with GHD, Inc. for a maximum of $190,674 for the term September 13, 2022 until one year after completion of the scope of services for the Sewer Lift Station A Tank Replacement Project, LB 22-03.
Attachments: 1. Agreement
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TO: Members of the Governing Board
FROM: Christopher Silke, District Engineer
REPORT BY: Anna Martinez, Assistant Engineer
SUBJECT: Approval of a Professional Services Agreement with GHD, Inc. for Design Services Related to Sewer Lift Station A Tank Replacement Project, LB 22-03


RECOMMENDATION
title
District Engineer requests approval of and authorization for the Chair to sign Agreement No. 230149B with GHD, Inc. for a maximum of $190,674 for the term September 13, 2022 until one year after completion of the scope of services for the Sewer Lift Station A Tank Replacement Project, LB 22-03.
body

EXECUTIVE SUMMARY
The District received $800,000 of American Rescue Plan Act (ARPA) funds through a Memorandum of Understanding with Napa County for the replacement of the main wastewater collection and storage tank at Sewer Lift Station A on February 8, 2022. The tank requires replacement due to deterioration of interior and exterior coatings, widespread pit corrosion along the wall panels, and corrosion of the metal roof dome - all caused by long-term sewer gas build-up in the tank above the high water line. A Request for Qualifications / Proposals (RFQ/RFP) solicitation for design services related to the replacement of the tank with a tank more suited to the highly corrosive nature of raw sewage, was publicly advertised on June 21, 2022. Two (2) engineering consultants submitted proposals by the July 28, 2022 deadline. GHD, Inc. ranked highest amongst the proposals submitted. Staff recommends approval of a Professional Services Agreement effective September 13, 2022 and expiring one year following completing the scope of services.

FISCAL & STRATEGIC PLAN IMPACT
Is there a Fiscal Impact?
Yes
Is it currently budgeted?
Yes
Where is it budgeted?
Fund 5220, Org 5220500, Project 22014
Is it Mandatory or Discretionary?
Discretionary
Discretionary Justification:
The existing tank could become compromised due to extensive pitting and corrosion, and the District could be ci...