Title: Director of Public Works requests the following actions regarding the "Scour Repairs at the Silverado Trail Bridge over Bell Canyon Creek Project - RDS 20-43: 1. Approval of the plans and specifications and authorization to advertise for sealed bids and opening of the bids at a time, date, and location to be published by the Director of Public Works pursuant to section 20150.8 of the Public Contract Code; and 2. Approval and authorization for the Chair to sign Amendment No. 2 No. 170826B with WRECO to extend the term of the Agreement by two additional fiscal years to provide additional engineering and construction support services for various projects.
Attachments: 1. Board Budget Summary, 2. Agreement
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TO: Board of Supervisors
FROM: Steven Lederer - Director of Public Works Public Works
REPORT BY: German Sierra-Frutos, Engineering Technician
SUBJECT: Approval of Plans and Specifications and Authorization to Advertise for Bids for "Scour Repairs at the Silverado Trail Bridge over Bell Canyon Creek Project", RDS 20-43 and Approve Amendment No. 2 to Agreement No. 170826B


RECOMMENDATION

title
Director of Public Works requests the following actions regarding the "Scour Repairs at the Silverado Trail Bridge over Bell Canyon Creek Project - RDS 20-43:
1. Approval of the plans and specifications and authorization to advertise for sealed bids and opening of the bids at a time, date, and location to be published by the Director of Public Works pursuant to section 20150.8 of the Public Contract Code; and
2. Approval and authorization for the Chair to sign Amendment No. 2 No. 170826B with WRECO to extend the term of the Agreement by two additional fiscal years to provide additional engineering and construction support services for various projects.
body

EXECUTIVE SUMMARY
The Bell Canyon Creek Bridge (No. 21C0001) over Silverado Trail is located just north of the intersection of Silverado Trail and Glass Mountain Road. This project will correct potential undermining of an exposed abutment footing which, if not repaired, would put the structure at risk.

WRECO, the design consultant previously hired by the County in support of this project, completed the design, plans, and specifications to replace the existing rock slope protection (RSP) under the bridge with larger RSP. WRECO's contract expires at the end of the fiscal year, and their services will be needed throughout the project. Thus Staff recommends that the Board approve Amendment No. 2 to WRECO's contract, the plans and specifications for the project, and authorize the Director of Public Works to advertise for sealed bids for construction.

FISCAL & STRATEGIC PLAN IMPACT
Is there a Fiscal Impact?
Yes
Is it c...

Click here for full text